Site icon Method Statement HQ

Testing & Commissioning Method Statement For Building Management System BMS

Below method statement is for testing and commissioning of DDC panels and FCU (fan coil units) with respect to building management system BMS.

Pre-Commissioning Checks for field Instruments

Check installation of all field instruments for correct location and position as instructed in the installation details of each instrument as well as instructions from supplier.

Check all field instruments cable for end-to-end continuity breaks and short circuits using multi-meter before terminating at field instruments.

Check all field instruments for correct number & type of cables as per the specified or recommended cable type.

Check all field instruments for correct wiring termination of field instruments as instructed in the installation details.

Check all field instruments for dressing, furling and crimping of wiring of field instruments.

Install controller housing, CPU, power supply and I/O modules as per installation details provided by supplier.

Check all internal wiring as per panel electrical wiring diagram.

Check for all field instruments cables including cables between controller and MCC to be available in controller cabinet with proper furling, dressing.

DDC PANELS – Commissioning 

All activities for all instruments and DDC controllers as mentioned in Pre-Commissioning Procedure mentioned above to be complete and documented by filling up the commissioning test sheets for each system.

Stable permanent power without any fluctuations in frequency or voltage to be available to DDC controller and field instruments.

MCC Commissioning

MCC to be powered and commissioned. All switchgear operations checked for start-up, shutdown and interlocks in Hand-Off-Auto Modes.

All mechanical/electrical equipment connected to DDC controller to be powered tested and commissioned

FAN COIL UNIT

HEAD END GRAPHICS

PRINTERS (ALARM & REPORTS)

Servers / Workstations: BMS software like EBI or whatever applicable should be installed on Servers / Workstations. Alarms reports are configured as per client requirements.

Network (IP Based) : Check that the communication link is up between the BMS Servers, Workstations, DDC Panels, LIP (LON to IP converters). 

Permanent Power: Stable permanent power without any fluctuations of frequency or voltage and backed by UPS to be available to BMS Servers, Workstations and to Networks equipment. Use multimeter to confirm Voltage and frequency fluctuations before powering up BMS Servers, Workstations and to Networks equipment, etc.

INTERFACE WITH THIRD PARTY SYSTEMS

BMS TESTING & COMMISSIONING PROCEDURE

DDC PANELS

Power-up DDC Controller:  check DDC Power Supply On/Off Switch is in OFF position. Check for 240VAC at MCB.

Download Software at DDC Controller: Set controller address. Set controller Date & Time. Download DDC controller application software as per instructions included with licensed software. Check for any system alarms.

Connect Field Wiring at DDC Controller & Check: Start connecting field instrument cables in the following sequence and fill up the recording sheets.

Digital Inputs:

Digital Outputs:

Analog Outputs:

Analog Inputs:

 FAN COIL UNIT COMMISSIONING

Power-up FCU Controller

HEAD END GRAPHICS (Commissioning & Sequence of Operation Check)

PRINTERS (ALARM & REPORTS)

INTERFACE WITH THIRD PARTY SYSTEMS

Once 3rd party systems are configured then match the values on the BMS graphics and on the 3rd party system’s display for different parameters in real time. The values may keep on changing on the 3rd party display but should match on both systems (BMS & 3rd party system) after a delay of few seconds.

Checking the Sequence of Operation

DDC PANEL, HEAD END GRAPHICS: When all field cables have been verified and checked, check and verify the sequence of operations as described in the Sequence of Operation Manual.

FAN COIL UNIT: Applications with DDC Controller to be checked.

Exit mobile version