Site icon Method Statement HQ

Method Statement For Testing & Commissioning Of Cooling Towers

The scope of this method statement is to determine the thermal capability of water cooling towers. Its main purpose is to describe instrumentation and procedures for the testing and performance evaluation of water cooling towers.

It is recognized that the data limitations specified throughout this Testing & Commissioning Procedure represent desired conditions which may not exist at the time the test is performed.

In such cases, existing conditions may be used if mutually agreed upon prior to test by client authorized representative, contractor, sub-contractor & third party personnel.

Before commencement of Testing & Commissioning activity, the supervisor/ engineer must ensure that:

All Installations & Pressure Testing of Pipe/ Duct works have been completed & approved by the client.

Determine whether the units occurs damages during the storage, installation & shifting of units into its site location.

Permission to start or Civil Clearances prior to testing & commissioning has been given by the main contractor.

All relevant Approved Shop drawings, manufacturer’s recommendations, specifications etc. for the testing & commissioning of the system shall be available & approved by the client.

Testing & Commissioning activities shall only commence when all associated works by the civil contractor has been completed, Installation activities & all associated works intended & connected to the Cooling Towers has been completed & approved by the client.

Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the Safety in charge at site.

Ensure that at the time of test, the tower shall be in good operating condition.

Water distribution system shall be essentially clear and free of foreign materials which may impede the normal water flow.

Mechanical equipment, if involved, shall be in good working order. Fans shall be rotating in the correct direction, with proper orientation of leading and trailing edges. Fan blades shall be at uniform angle that will yield within +/- 10 % of the specified horsepower loading. In addition, centrifugal fans shall be free of foreign material and properly secured to the shafts.

Drift eliminators shall be essentially clear and free of algae and other deposits which may impede normal air flow.

Fill shall be essentially free of foreign materials such as oil, tar, scale or algae.

Water level in cold water basin shall be at normal operating elevation and shall be maintained substantially constant during the test in order to provide proper airflow to the fill.

Make-up and or blow down streams may be stopped during the test if other test condition requirements are not adversely affected.

Procedures for Testing & Commissioning of Cooling Towers

 Operating /Test Conditions

The test shall be conducted within the following limitations:

The wet-bulb and dry-bulb temperatures shall be the inlet values, measured in accordance to this test procedure.

The wind velocity shall not exceed the following:

The following variations form design conditions shall not be exceed:

The water shall be distributed to all operating cells and/ or parts of the tower.

The total dissolved solid in the circulating water, as determined by evaporation, shall not exceed the greater of the following:

For a valid test, variations in test conditions shall be within the following limits:

After reaching steady state conditions, the duration of the test run shall be not less than one hour. If thermal lag time is greater than five minutes, the timed test period shall be at least 1 hour plus thermal lag time.

Readings shall be taken at regular intervals and recorded for future reference.

Measurement Procedures

Water Flow Measurements

Water Temperature Measurements

Inlet Air Temperature Measurements

Wind Velocity Measurement

The wind velocity measurement shall be made with an anemometer of the rotating cup type. Measurement shall be made in an open and unobstructed location within 100 feet of and to windward of the tower at a point 5 feet above basin curb elevation.

Fan Driver Power

For mechanical-draft and fan-assist towers, power shall be determined as power input to the motor or driver. In the case of electric motors, power input shall be determined by measurement of voltage, current and power factor, or by direct measurement of the Kilowatt input. If performance guarantee is based on driver output, efficiencies assigned for the driver may be used.

Cooling Tower Start-up Procedure

Cleaning

Inspection

Start-Up

Exit mobile version