Site icon Method Statement HQ

METHOD STATEMENT FOR INSTALLATION OF WIRING DEVICES & CEILING ROSE

PURPOSE

The purpose of generating this method statement is to define the procedure step by step to implement the correct practices for Installation of Wiring Devices & Ceiling Rose for Electrical System through the guidelines contained herein so as to ensure that the job execution complies with the requirements of contract specification and serves the intended function to satisfactory level.

SCOPE

This method statement covers all processes related to Installation of Wiring Devices & Ceiling Rose for Electrical System as the following:

This procedure is to be read in conjunction with the relevant ITP, outlining the responsibility and the quality verification to be performed by various parties.

REFERENCES

DEFINITIONS

PQP: Project Quality Plan

PSP: Project Safety Plan

QCP: Quality Control Procedure

HSE: Health, Safety and Environment

MS: Method Statement

ITP: Inspection Test Plan

QA/QC: Quality Assurance / Quality Control

RESPONSIBILITIES

Project Manager

The work progress shall be carried out as per planned program and all the equipments required to execute the works shall be available and in good condition as per project planned.

The constant coordination shall be implemented with the Company, Safety Engineer and Sub-contractors for the safe and proper execution of the work.

Specific attention is paid to all safety measures and quality control in coordination with Safety Engineer and QA/QC Engineer and in line with PSP and PQP. 

Engineer-In-Charge

The method of Installation of Wiring Devices & Ceiling Rose shall be implemented according to the project specifications and approved shop drawings.

Provision of all necessary information and distribution of responsibilities to his Construction team.

The work progress shall be monitored in accordance with the planned work program and he will provide reports to his superiors.

The constant coordination with the Safety Engineer to ensure that the works are carried out in safe working atmosphere.

The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for the inspection for the finished works.

He will ensure the implementation of any request that might be raised by the Company.

Efficient daily progress shall be obtained for all the equipment and manpower.

He will engage in the work and check the same against the daily report received from the Foremen.

The passage of all the revised information to the Foremen and ensure that it’s being carried out properly.

Coordination with the surveyor and plan the survey works in advance as per the work sequence.

QA/QC Engineer (MEP):

The monitoring of executions of works at site and should be as per the approved shop drawings and specifications.

Ensure ITRs are being raised for activities in timely manner and inspected by the Company.

He will follow and carried out all the relevant tests as per project specifications.

Obtain the required clearance prior to Company’s inspections.

Should acquire any necessary civil works clearances and coordination.

Site Foreman

The carrying-out of work and the proper distribution of all the available resources in coordination with the Site Engineer on a daily basis.

Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.

Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.

Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.

Safety Officer

The implementation of all safety measures in accordance with the HSE plan and that the whole work force is aware of its proper implementation.

The implementation of safety measures is adequate to maintain a safe working environment on the work activity.

Inspection of all the site activities and training personnel in accident prevention and its proper reporting to the Construction Manager and the Project Manager.

The site is maintained in a clean and tidy manner.

Ensure only trained persons shall operate the power tools.

Ensure all concerned personals shall use PPE and all other items as required.

Ensure adequate lighting is provided in the working area at night time.

Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with ladders.

Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.

Ensure safe access to site work at all times.

EQUIPMENT / TOOLS

PROCEDURE

Safety

Ensure only trained persons shall operate the power tools.

Ensure all concerned personals shall use PPE and all other items as required.

Ensure adequate lighting is provided in the working area at night time.

Ensure service area/work area openings are provided with barricade, tape, and safety nets.

Work Sequence And Methodology

Check all material delivered to site is inspected properly by QA/QC Engineer and check if it is stored properly as per manufacturer’s recommendations.

MIR shall be raised for the inspection of materials, Wiring Devices & Ceiling Rose, received at site to the  Engineer.

Work shall be carried out by the site staff under strict supervision and guidance of the concerned Supervisors / Foremen / Engineers.

The MEP QA/QC Engineer shall check all the installations as per the Installation Check list.

IR shall be prepared by MEP QA/QC Engineer and will be submitted to consultant for their inspection and approval.

MEP QA/QC Engineer shall coordinate with other contractors and arrange inspection for installation to the Engineer.

MEP QA/QC Engineer is responsible for all installation activities for getting the work inspected and approved by Engineer.

Installation of Wiring Devices & Ceiling Rose

ATTACHMENTS

Exit mobile version