Method Statement for Assembling Erection Installation & Management of Mast Climber

The Scope of this method statement covers all operations and associated activities involved in safe and efficient management of Mast Climber including assembling, erection, and installation for efficient and effective utilization in execution of project works.

Following equipment shall be arranged:

The Scanlnter SCANCLIMBER SC5000 can be used either as a single or twin mast climbing platform. It is designed to position men with their tools and other necessary equipment and material for the working in great heights.

SCANCLIMBER SC5000 can be used during all kinds of works: assembly, finishing, cladding and painting of buildings, facade work and industrial objects. It can be installed indoors as well as outdoors.

The unit is operated up and down with push-buttons on remote control box. On the box there is also an emergency stop push-button.

SCANCLIMBER SC5000 consists of chassis, mast and platform modules which are connected to the lifting case.

All erection/assembly and disassembly and other operations will be carried out as per instructions manual under Supervision of qualified Erection Supervisor.

ASSEMBLING / ERECTION PROCEDURE:

SC5000 mast climbing work platform has been designed with intention of its easy and quick assembly.

Partial assembly, that should be checked before taking the Scanclimber into use:

Mast sections, platform sections and wall anchors must be installed according to the instructions given in the manual.

PREPARATORY WORKS

The following preparatory works to be carried out:

WALL ANCHORING

ASSEMBLY INSTRUCTIONS

SINGLE MAST ASSEMBLY

A- Freestanding maximum lifting height / platform length: 13/16.9 m and maximum wind speed 12.7 m/s.

B – Freestanding maximum lifting height / platform length: 18/16.9 m, maximum wind speed: 12.7 m/s.

The following should be done:

a) Switch on power with platform electric box main switch.

b) Switch on power with cable drum main switch.

c) Check, if the phase relay in the platform electric box is red.

TWIN MAST ASSEMBLY

Same procedure as Single mast assembly. For further details refer to the instruction’s manual,

PLATFORM DISASSEMBLY

Platform disassembly should be carried out in the reverse order to the assembly.