Site icon Method Statement HQ

Method of Statement For Installation of Compressed Air Piping System for Chillers

1. PURPOSE

This method of statement covers the on construction project site installation of the compressed air piping system for the operation of the chillers.

This method statement covers following type of works:

Power Plant Compressed Air Systems

Factory assembled packaged air compressor complete with:

–  Rotary screw air compressor

–  Receiver

–  Filtration facilities

–  Instrumentation & Control Panel

–  Refrigerated air dryers.

2. PRE REQUIREMENTS – GALVANIZED PIPEWORK

Construction department will check all materials and documentation relevant to a particular section of works prior to the commencement of work.

This approach will ensure that all materials and works are of the correct type as per the client requirements.

Prior to the commencement of any piping construction activity, safety inspector will check areas and access to confirm that they are in a suitable condition for construction works to commence.

Before commencement any construction activity, pre-inspections will be carried out on all material prior to them leaving the storage area.

3. INSTALLATION METHOD STATEMENT

Ensure that horizontal and vertical pipe runs are correctly aligned and supported as indicated in the table below for galvanized pipework.

NOMINAL BORE

 OF PIPE

INTERVAL FOR

 HORIZONTAL RUNS

INTERVALS FOR

 VERTICAL RUNS

mm

m

m

15

0.75

1.5

22 to 28

1

1.8

28 to 35

1

2

42

1.2

2.4

54

1.4

3.5

Install the compress air pipework with falls not less than 1 in 80 in the direction of flow.

Provide drainage points at intervals not exceeding 30 meter.

Drain sets will be piped to the nearest suitable floor waste.

3.1 JOINTING PROCEDURE FOR GALVANIZED TUBE

Screw the pipe work and joints up to and including 50 mm mild steel pipe.

Prepare the threads at pipe ends using an appropriate threading machine.

Make sure that the machine die head is suitable to cut tapered type threads.

Cut the threads to the correct thread length.

After cutting the suitable thread burrs, surplus oil and swarf will be removed prior to the selected fitting being screwed in place.

Threads shall be applied with thread joint compound of the approved type.

By means of an appropriate pipe wrench, the selected fitting will be screwed onto the pipe thread to the correct tightness required without causing any damage to the pipe/fitting.

When pipe and fitting is fully tightened, clean of any excess jointing compound, and paint exposed threads with approved cold galvanizing compound.

4. FINAL PIPING CONNECTION

Final connections to compressor will be full line size flexible connections of type shown on the construction drawing located as close as possible to the compressor.  Ensuring pipework is adequately supported independently to the flexible connectors.

5. PIPEWORK PRESSURE TESTING

Prior to the start of pneumatic testing all other works on the system will cease and personnel adjacent to the area will be informed of the intention to test.

Connect pressurization pump / equipment to the piping system including a pressure gauge to register line pressure, isolated from the equipment.

Pipe pressure test will include the usage of safety release valve.

The test pressure will 1.5 times the system working pressure, hold the pressure constant for 30 minutes.

Attain the target pressure by raising the pressure equally in three stages.

During any of the three periods if a leakage is apparent in the system it will be identified and logged, but no remedial work will be undertaken.

All remedial work will be carried out after the system has been bleed to atmospheric pressure.

Upon completion of any remedial work the system will be re-pressurized as before.

When the system is charged to its test pressure the air temperature in the system must be allowed to stabilize and the pressurization equipment disconnected.

6. EQUIPMENT INSTALLATION METHOD

All documentation and certification relevant to the Packaged Air compressor will be checked by the Construction Department prior to the commence of installation, ensuring that they are of the correct type as review by the client.

All lifting and handling procedures will conform to the manufacturers instructions ensuring at all times that Packaged Air Compressor is not subjected to undue stress.

Compressor and associated equipment will be carefully plumbed and aligned, then bolted and securely anchored to “Housekeeping” pad.

After alignment is complete, supervisor in charge will ensure that vibration isolators are of the correct deflection. Final adjustments will be made at pre-commissioning stage.

It will be ensured that all completed installations look neat and tidy, and that there is adequate spacing between pipe lines and other services allowing easy access for operation and maintenance.

The supervisor and the QC officer will continuously monitor the activities to ensure that all components indicated on the approved construction drawings have been installed and that the installation is in accordance with the contract requirements and manufacturers recommendations.

Protect all installation work to avoid any damage from workers and other activities.

 7. SAFETY AND ENVIRONMENTAL CONSIDERATIONS

In order to ensure that all compress air system works will takes place in a safe manner, the company will consider suitability of the following:

Work on height

Use Of Suitable Tools

 Welding

Pressure test

8. RECORDS & REFERENCES

Exit mobile version