Main Sub-Main Distribution Boards Testing and Commissioning Procedure

Method Statement For The Testing and Commissioning of Main Sub-Main Distribution Boards (MSMDB) Sub-Main Distribution Boards (SMDB) Distribution Boards (DB) and Consumer Units(CU)

TESTING, COMMISSIONING AND START UP PROCEDURES

Preparation

Prior to system operation the Contractor together with the Engineer visually inspects and attests that the system is ready for operation. The following shall be observed:

Punch list: The contractor shall see to it that all the punch list items that may directly affect the system tests were all complied with and/ or resolved with the Engineer/ Client.

Notification: The Contractor shall notify the Engineer and/ or Client representative of the time and date when the test/ inspection shall be performed. The Contractor shall notify the Engineer and/ or Client representative 48 hours before the actual inspection to enable them to witness the tests. The values will be recorded and submitted for further approval.

Testing procedure MSMDB’s and SMDB’s

The following tests are to be carried out in a distribution board:

Test equipment/ instruments:

Insulation resistance test – Procedures

Electrical/ Functional Checks – Procedures

Testing procedure of DB’s & CU’s

The following tests are to carried out in a distribution board:

Electrical/ Functional Checks – Procedures

Before Energisation

Check:

Switch on Process

Acceptance:

After the system is thoroughly tested and inspected and all comments have been duly complied and rectified, the Engineers shall sign the Acceptance Certificate certifying that the system is fully accepted and shall be ready for handing over to the owner.