Method Statement Irrigation Systems Piping

Only approved material shall be used. Delivered material shall be stored at stores and shall always be subject to client’s representative inspection. Special shaded pipe racks shall be constructed to store pipes. Fittings and irrigation materials shall be stored inside containers that will be kept closed at all times.

Transportation: All materials will be transported to site with due care and protection as per manufacture’s recommendations. uPVC or trailer and will never be dragged or dropped on the ground.

Material Inspection: All materials received will be inspected for make as per approvals, size and damages. Materials found unsuitable shall be removed from site.

Protection: All materials shall be shipped or otherwise conveyed in such a manner as to assure no damage. All boxes shall be securely sealed and clearly marked with the name of the manufacturer. All pipes shall be protected from crimping, crushing and splitting. All non-metallic system components shall be protected from sunlight exposure as per manufacturer’s recommendations.

Works and materials shall be protected from damage during storage, handling and construction. Particularly, non-metallic pipes and fittings shall be protected from direct sunlight during storage. Facilities of the necessary dimensions shall be provided and maintained for storage of all non-metallic irrigation materials in their entirety. All non-metallic materials shall be handled carefully and stored under cover to avoid damage. Pipes that have been damaged or dented will not be used in this work and to be removal from the site immediately.

Openings into the system, apparatus and equipment shall be securely covered, both before and after being set in place, to prevent obstruction in the pipes and the breakage, misuse or disfigurement of the apparatus or equipment.

Barricades, guards, warning signs and lights as necessary or required, for the protection of the public and the work force shall be provided.

All open ends shall be close by end cap provided by manufacture /supplier.

Utilities: The location of the existing underground utilities shall be determined and the works performed in a manner which will avoid possible damage. Hand excavation, as required shall be carried out to minimize the possibility of damage to existing underground utilities.

Irrigation Pipe Placing and Laying

Closing of Pipe and Flushing Lines:

Pressure Testing