Site icon Method Statement HQ

METHOD STATEMENT FOR TESTING & COMMISSIONING OF PRESSURIZATION UNIT

The purpose of this procedure is to define the step by step method to implement the correct practices for the pre-commissioning & commissioning of Pressurization Unit through the guidelines contained herein so as to ensure that the job execution complies with the project requirements/specifications and serves the intended function to satisfactory level. The scope of this Method Statement is to define the method of Testing and Commissioning of Pressurization Unit installed within the project in accordance with the part of commissioning checks at site.

References:

Tools & Testing Instruments :

Site Quality Control

In general, it shall be ensured by Site Engineer that product manufacturer’s recommendations are followed and shall be monitored by QA/QC Engineer.

Project Engineer shall further oversee the Pre-commissioning and commissioning activity as per the approved method statement for Start-up and Commissioning of Pressurization Unit.

Pressurization Unit shall be tested under direct supervision of manufacturer / local dealer’s representatives or specialist contractor.

Pre-Commissioning & Commissioning Procedure

Mechanical Checks

Electrical Checks

Start-up and Testing Of Pressurization Unit

Before commencing the commissioning procedures detailed below, ensure that the system is full, and that the unit water tank is full.

Sequence of Operation of Pressurization Unit

  1. H/O/A switch on off position, the relevant pump stops.
  2. H/O/A switch on hand position, the relevant pump starts provided there is enough water in the feed tank.
  3. H/O/A switches of all the pumps on Auto position, the pumps works automatically based on the pressure demand.
  4. On System pressure demand (Press. SW makes), the pumps starts.
  5. At system pressure satisfaction (Press. SW breaks), the pump stops.
  6. Duty Selector switch in position 1. Pump – 1 will work and the second is standby.
  7. Duty Selector switch in position 2. Pump – 1 will work and the first is standby.
  8. If one pump trips on fault, the second pump will start automatically to meet the same demand.

Safety Requirements

Related Records

Exit mobile version