Site icon Method Statement HQ

Construction Method Statement For Installation of Chilled Water Piping System

This method statement covers on site installation of pre-fabricated and site fabricated mild steel pipework including supports, expansion and anchor points for chilled water system.

This procedure is to define the method used to ensure that the Chilled Water Pipework System installation is as per project requirements.

System comprises all pipes, tubes, valves, fittings, reducers, expanders, nipples, vents, bleed off, expansion and contraction devices, hangers, brackets, anchors, supports, sleeves, plates and all accessories.

By following this method statement you shall ensure that components connected thereto as an integrated pipework system, installation final connections and workmanship, is correct and acceptable. Also you shall make sure that all the work conforms to the contract documents and General Specifications. Materials required to submit and reviewed the Client.

In addition to piping works, this procedure will ensure that the pipe insulation to all supply and return mains, headers, branches, risers, drips, run-outs, pump suction and discharge, pipework, fittings, flanges, valves, expansion and movement devices and flexible connections etc.

Pre Requirements before installation

All materials and documentation relevant to a particular section of works will be checked by the Construction Department prior to the commencement of work ensuring that these are of the correct type as reviewed by the Client.

Before commencement of any construction works, pre-inspections will be carried out on all materials prior to them leaving the storage area. Invite the client or consultant to attend the material receiving inspections as per their discretion.

Prior to the commencement of any construction works, areas and access will be inspected to confirm that they are in a suitable condition for safe construction works to commence.

Chilled Water Piping System Installation Method

Mechanical Supervisor will instruct tradesmen regarding the execution of the works and will distribute all necessary approved construction status drawings of the latest revision.

The supervisor will also check that tools and equipment available are in compliance with the contract requirements.

Coordinated chilled water piping installations will generally run parallel to the alignment of the adjacent building surface’s, and as close to the construction as possible, or in certain cases, slope towards a drain point.  All high points within pressure pipes will be vented by means of automatic air vents.

Drain outlets will be provided at all low points of the system, and means of air venting at all high points of the system.

Chilled water piping over service passages for plant operators, will be installed to a minimum height of 2 meters from finished floor.

Pipework will rest freely on supports and carefully aligned prior to final connection to each other, or any other pertaining equipment as listed in the scope of works.

Where possible all pipes of straight runs will be lined up with facilities for pipes to be rotated for welding joints – bottom welding will be excluded as far as is possible.

Pipework connections to final equipment will be made by the designated flexible connection where required.

All branch connections will be factory fabricated, if site fabrication is necessary it will be of the same standard.  Sample of material will be submitted for approval prior to any production work starts.

 All tees will be of the same size as the pipes connected to them, bushed outlets will only be used if the required outlet size is not of standard manufacture.

Reductions will be made by means of straight through reducing sockets, reductions on bends by bushes will not be used. 

Valves and other in line equipment will be installed where indicated on the approved construction drawings, installation will be in accordance with the manufacturers recommendations and will be consistent with the flow direction of fluids.

Flexible connection, anchors, guides expansion joints and loops will be installed where indicated on approved construction drawings.

When installing universal and swing type expansion joints the axial movement of the building structure shall be taken into consideration at the time of installation.

All chilled water piping system will be provided with adequate removable sections to assist cleaning and for ease of maintenance operations, just the equipment connections.

Chilled water piping jointing requirements

Flanged Jointing Procedure

Fixing of flanges to pipe ends will be either screwed or welded type.

The type selected for a specific application will be as per approved details and in compliance with the specification requirements.

Gaskets will conform to ANSIB 16.21 and ASTMD200.

Follow below steps:

 Procedure of Mechanical Joints

The mechanical joint consists of a  split coupling housing and an insert-able rubber gasket.

To accept the mechanical joint the pipe ends must be grooved. Grooves will be achieved with the use of an appropriate grooving machine.

Pipe grooving and joint will be installed in accordance with the manufacturers recommendations.

Prior to any prefabricated pipework being released from the pipe fabrication shop for installation on site, the shop manager or his representative will complete the “material release note for prefabricated pipework” so as to ensure compliance with the specification requirements.

HEALTH SAFETY AND ENVIRONMENTAL REQUIREMENTS

During the installation of chilled water piping system following shall be considered.

A- Work on height

B- Tools

C- Welding

D- Handling equipment

E- Pressure test

A- Work on height

Mobil scaffold & Ladders

 B- Tools

C- Welding

In order to ensure that all welding takes place in safe manner, the following will be considered:

C-1 Welder

C-2 Equipment

On construction site, arc welding is usually carried out with direct current (DC), supplied from diesel driven generator. Welding leads and welding return cables are frequently dragged over rough surface, their insulation should therefor be suitable for resisting fear and wear.

C-3 Working location

D- Handling Equipment

Mechanical handling

Chain Blocks

E- Pressure test

Exit mobile version