Site icon Method Statement HQ

Welding Procedure | Arc Welding Machine

This welding procedure or Method statement describes in detail the welding process for pipe work and the welder’s qualification test procedures. This includes addressing programs for implementing commitments regarding the quality of welding works.

Scope and Purpose
This document outlines the method for executing welding procedure for pipe work and welding procedure qualification test for ARC Welder. This method statement covers all piping welding works for Project either shop fabricated or site installed.

The procedure provides guidance for assessing the activities for jointing mechanical piping system. This guidance is based on the requirements set forth in the Safety Requirement Document (SRD) and The Quality Assurance Program (QAP).

Objectives
This document provides guidance in implementing an effective program for pipe welding works. This includes addressing programs for the following:

This procedure is one component of a complete construction and inspection program.

                                               Arc Welding Machine

This and other procedures will be used, as needed, to provide assurance that construction activities are being conducted as required by the specification and manufacturer procedures. It is not expected that completion of the entire procedure will be accomplished during any one inspection and/or every time the inspection procedure is used. It is a continuing activity until all piping networks are installed and tested.

Inspection and Recording Requirements
The engineer should verify that the supervisor/foreman with construction responsibilities for the pipe welding works is familiar with this method statement and is issued with copies of the inspection checklists and test plans. The engineer should satisfy procedures provided by QA/QC inspections to ensure the pipe welding works meet specified engineering requirements and drawings. As part of the assessment, the QC Inspection Procedures, must ensure a quantitative or qualitative acceptance criteria for determining the prescribed activities have been accomplished satisfactorily.

The QC inspection personnel, in coordination with Site Supervisor, should verify that the quality of the pipe welding works and related testing activities are within the project design specifications requirements. The Supervisor should verify that the pipe welding works is accomplished in accordance with the specifications and the manufacturer’s procedures. The Supervisor should verify any as-built record of pipe welding works and testing, and confirm that the information meets the project requirements.

Inspection Guidance
Pipe welding works need to follow strictly established codes and safety procedures. Care should be taken to ensure that applicable codes and standards be strictly adhered to during pipe welding works. The Supervisor can choose to follow the most appropriate welding technique applicable at such a given time and in coordination with the construction progress, QA/QC inspection and testing requirements. The Engineers should use judgment in determining sample selection focusing on examination of the most important aspects of the particular welding activity being inspected. The intent is to establish a high level of assurance that the end product meets the project requirements. Review the implementing procedures and safety standards for the pipe welding works provided by the QA/QC. The QA/QC inspectors should verify that the procedures are approved, and specify the requirements of the design and/or from the manufacture’s technical manual(s) and codes or standards prescribed by the Client.

Training and Qualification of Arc Welder

The Supervisor should verify that the personnel have sufficient knowledge of the procedure requirements. The Supervisor should review any training and qualification records for those individuals who shall do the task to determine whether they are skilled enough to follow the procedure before the actual work is carried out.

Preparation of Materials and Execution of Works for welding procedure:
• General
• Pipe Joint Preparation
• Pipe to Pipe Fit Up
• 45° Elbow to Pipe Fit Up
• 90° Elbow to Pipe Fit Up
• Tee to Pipe Fit Up
• Flange to Pipe Fit Up

Welding Procedure Qualification Test Requirements
• Welding Process
• Base Metals
• Filler Metals
• Position of Groove & Weld Progression
• Temperature Requirements
• Postweld Heat Treatment
• Type of Gas
• Electrical Characteristics
• Travel Speed & Passes
• Laboratory Test Results

Description of Activities

General

Pipe Joint Preparation

Pipe to Pipe Fit Up

Lay the two pipes on top of the pipe stand or adjustable support, with each pipe ends aligned near each other using adjustable bolt stopper as shown on Figure 2 below.

Note : For larger sizes only, 4”dia. and above

45° Elbow to Pipe Fit Up

90° Elbow to Pipe Fit Up

Tee to Pipe Fit-Up


Flange to Pipe Fit-Up

Figure  – Flange to Pipe Fit Up

TYPICAL DETAILS OF ADJUSTABLE BOLT STOPPER USE FOR PIPE FIT UP and ALIGNMENT
Note : For larger sizes only, 4”dia. and above

List of Main Welding Equipment, Tools, Instruments

A. Boom truck
B. Chain blocks (1Ton – 5Ton Cap.)
C. A-frame (steel fabricated)
D. Nylon sling or straps (New and tested)
E. Set of shackles
F. Adjustable bolt stopper
G. Adjustable pipe supports
H. Spirit level
I. Alignment Tools (Plumb Bob, Chalk line, Nylon String Line, Felt Tip Marker)
J. Welding Personnel Protective Equipments
K. Hand tools
M. Steel measuring tape
N. Angle & Straight Grinders
O. Welding Machines
P. Steel Scaffolding and Ladders

Health, Safety and Environment Measures
Preparation
Notify all concerned in site for the date of material delivery.
– Coordinate with Safety Department for delivery trucks access routes.
– Ensure all workers involved in the hauling operation put on PPE all times.
– Brief individual worker the roles and responsibilities of each.
– Ensure transporter route is cleared of obstruction.
– Coordinate with Construction Department for Pipe Hoisting area.
– Ensure designated hoisting area is cleared of obstruction.
– The lorry transporting the pipes will be guided to the designated hoisting area and released all the latching belts only after the lorry parked firmly.
Pipe Lifting
– Ensure safe work procedure for lifting operation is observed.
– Ensure proper lifting method – with the correct equipments are used.
– Ensure the pipes are firmly placed on the designated location before releasing the hoisting hook.
During Site Execution
– Ensure workers are distributed to each designated place.
– Ensure workers at all times to be in proper gear where required.
– Ensure all workers assigned are involved in its particular task.
– Brief individual worker the roles and responsibilities before start work.
– Ensure the pipe lengths to suit site routes into designated work area.
– Ensure pipe support systems are installed accordingly as required.
– Ensure all tools to be used have been inspected and tag by Safety Dept.
– Ensure work areas are clearly marked to restrict access to authorized personnel only.
– Ensure that equipments to be used are properly tagged and checked.
– Ensure that arc welders are qualified, with the correct PPEs, and well versed on the job at hand with the latest revised drawing/s.
Housekeeping
– Maintain cleanliness and orderly stocking of materials & tools.
– Pick up and dispose wastes & other debris prior to leaving site area.
– Remove safety yellow tape or other warning devices that were used to control access to the work area.
– Store tools, equipment and unused materials properly at the end of the workday.

Safety Inspections
– It shall be responsibility of the Supervisor to routinely inspect the physical areas under their control in pipe welding procedure. This inspection shall include determining if pipes, supports, scaffolds and ladders are appropriately installed and/or use, and if the job site is cleaned up after the day’s work.

INSPECTION CHECKLIST FOR WELDING MONITORING
Report No. :…………
Contractor’s Name :….… ………….
Description of Works : ..…Pipe Welding……….
Reference No. : …………………………….
Date Prepared : ……………………………
Specific Location……………………………… Inspection Requested : Date …………… Time
…………….
ITEMS TO BE PERFORMED Accept Reject Hold Remarks
1. WELDING ELECTRODES & CONSUMABLES
1.1 Type of Consumables
1.2 Type used is per approved submittal (Yes/No)
1.3 Storage condition & handling satisfactory

2. WELDING PROCEDURE MONITORING
2.1 Type of Joint
2.2 Joint Alignment
2.3 Champer uniform & free of ripples or notches
2.4 Root Face ( height per approved WPS )
2.5 Tack welds
2.6 Root gap and free from foreign matter
2.7 Interpass cleaning & slag removal
2.8 Root Pass inspection
2.9 Interpass temperature
2.10 Electrical requirements
2.11 Welding speed & number of passes
2.12 Welding Process (SMAW/GTAW/SAW/GMAW)

3. VISUAL WELDING INSPECTION
3.1 Welder stamp identified (Hard Stamped)
3.2 Joint Number
3.3 Welds acceptability per code
3.4 Width & height of capping pass acceptable

Exit mobile version