Site icon Method Statement HQ

Method Statement for Piping Fabrication and Installation

This document covers the sequence of activities for Fabrication, Erection and Installation procedure for Metallic Piping (Carbon Steels, Stainless Steels, Nickel Alloys) systems and to ensure the compliance to the above activities with the contractual applications, applicable standards and HSE requirements.

Below is list of necessary equipment’s and tools for the piping fabrication and installation activities.

Equipment’s

Tools

Health Safety and Environmental Requirements

In workshop

Workshop Safety Procedures shall be strictly followed by all personnel’s.

Safety Plan at the workshop will be covered by the Health, Safety and Environmental Management System (HSEMS) of the contractor.

At site

HSE Manager shall ensure that the work is performed accordance to the approved Construction Safety Manual and precautions specified in the work permit.

He shall ensure that barricades, warning tapes, warning signs, fire fighting equipment’s and first aid kits are readily at the working area.

Tool box talk shall be conducted on a daily basis to inform the workers of the recent safety issues and incidents and to get feedback of any unreported unsafe acts. Feedback will then be processed and resolved.

Accident Prevention Safety Procedures

Area shall be barricaded adequately with warning barriers prior to any lift.

All equipment shall be checked for good conditions before commencing the work.

Unauthorized persons shall be excluded from the area.

Lifting equipment capacity and correct load slinging will be verified.

When lifting, the personnel shall not remain in the lifting equipment work area.

Adequate standard shall adopted for the construction of stages, planks, scaffolds, etc.

Adequate caution boards and warning signs shall be provided.

All lifting equipment shall have valid certificates.

Only trained and authorized personnel shall operate the hydraulic lift.

All lifting gears and shackles used shall be approved type with valid load test certificates.

Electrical installations and equipment shall conform to standards.

Trained fire watchers shall be appointed as per requirement.

Sufficient fire extinguishers shall be provided close to the welding, cutting and other hot works.

Welding areas shall be covered with fire blankets.

Consumable materials within 15 meters of welding operation shall be cleared.

Application, maintenance, storage of electric, and oxygen cutting welding units shall conform to applicable standards.

Do not stand under suspend loads.

On completion of job, the area shall be cleared of any materials and keep clean and tidy.

Hazard analysis for hazardous operation shall be carried out prior to commencing the works.

Roles and Responsibilities

Construction Manager

Responsible for overall site management, dissemination or execution of quality procedures that meets project requirements.

Establishment of construction organization, monitor job quality, schedule control and overall project management.

Construction Superintendent

Shall be responsible for the execution of pipe fabrication and installation work as per this procedure.

Monitoring and control of activities pertaining to the pre-fabrication erection and installation of piping and its components, compliance with HSE procedure.

Shall report to construction manager.

Field Engineer

Field Engineering Inspection and supervision in the area of piping works and ensuring implementation and adherence to Project Specifications, Procedures and HSE policies.

Shall provide technical support to the operation of piping works and ensure that piping fabrication and erection, inspection and testing meet the project specification ensuring with latest IFC.

Continuously check and review the changes status during the work.

Shall control of all kind of resources and coordinate with construction superintendent on execution of work and ensure productivity.

Construction Supervisor

Shall ensure that all site activities are performed in environmentally safe and responsible manner accordance with HSE and follow-up all safety procedures, permit to work, etc.

Shall supervise piping works and ensure the compliance with established construction schedule and project requirements as per applicable specifications and standards.

Lifting Supervisor

Shall co-ordinate all lifting activities and ensure that only certified equipment’s and trained crew are participated in the lifting.

Shall ensure that the ground conditions are safe for any lifting operation, and take measures to rectify the unsatisfactory and unsafe conditions.

Planning Engineer

Shall be responsible for monitoring progress throughout the construction process and comparing this with the projected schedule of work with introducing appropriate logistics solutions and resources.

He shall be responsible for day to day micro planning in coordination with field engineer and construction superintendent and report activities to project control manager.

QA/QC Inspector

Shall be responsible for inspection on production of pipes, fittings and spools to ensure the procedures are being followed in order to ensure that quality standards being achieved as per Project procedures, requirements and specifications.

Shall be responsible for maintenance of NDT records & Project documentation.

HSE Team

Shall be responsible for the implementation of the project HSE procedures before and during the execution of Piping fabrication and Erection.

He shall be responsible for check for any unsafe conditions on the working areas and liaise with field supervisor ensuring that the work is carried out as per approved Project Safety plan and procedure.

Piping Fabrication and Installation Procedure

Ensure that the document received bear the stamp “Issued for Construction”  and are of latest version.

The documents submitted/referred with this method statement shall be considered as an integral part of this method statement and shall be read in conjunction with the same.

Engineering drawings and documents received shall be clearly understood to find out the services, material specification, size, thickness, QA/QC requirements, pipe routing quantity etc. line wise and area wise.

Make sure that all the Quality Control and Pre-Construction formalities, approvals, and preparations are done sufficiently in advance to start the construction activity as per the schedule.

A checklist of all requirements shall be made internally to avoid any omission of them.

General Requirements

Proper HSE material handling procedure must be followed during material receiving, storing and delivery.

All materials shall be assigned for the storage of different piping materials specifications before receiving/ordering.

Separate area shall be assigned for the storage of different piping materials.

Pipes shall be stored in open area resting on wooden sleepers, fittings, bolts, nuts and gaskets shall be stored in shelved containers.

Storage and issue procedure of piping materials shall be in time with the requirements.

Handling and transportation of piping materials shall be done with utmost care to avoid any damage.

QC inspector shall conduct visual inspections, check color code, material certificates or manufacturer’s test reports (including size, wall thickness, rating, material code, heat no, quantity).

Material Receiving, Storage and Handling

The following procedure shall be followed for receiving, storing and delivery of all the materials.

Store Superintendent shall be responsible for delivering all materials and documentation to the job site in good condition.

All materials and documentation will be inspected immediately upon receipt by client QC inspector to determine that all items included in the Bill of Materials have been supplied, to assure that all documentation has been received and to check for any damage.

All materials shall be requested or received as per pre-fabrication or erection sequence or site requirements as per the Client Master Schedule which is agreed & approved by the consultant.

The receiving materials or equipment found defective or presenting non-conformance that shall be clearly marked out and shall be returned to corresponding authority.

Material shall be stored at defined locations based on material classifications, i.e. Carbon Steels, Alloyed Steels, Stainless Steels, non-ferrous material etc.

Large-sized fittings, flanges and valves shall be stored on wooden pallets and no material is allowed to rest or store directly on ground at all time.

All small sized fittings, flanges and valves, and all of gaskets shall be stored on racks/shelves.

All bolts, washers and nuts shall be packaged and delivered in rigid, weather-proof containers.

Flanged openings shall be fitted with plywood covers or fitted PVC flange covers, threaded openings are to be closed with plugs or similar, pipe openings shall be cover with end cap to prevent accumulation of dust or foreign material.

Ensure the material is secured properly so that it does not fall, roll or move from its storage position. Pipes will be supported at bottom with kegs/wooden blocks at least at three points and choked with wedges.

Materials stored in open areas will be barricaded and indicate the type of material and the hazard it poses, if any.

Coated pipe shall be handled at all times in a manner that prevents damage to the pipe walls (shall not be rolled or dragged on the ground), bevelled ends and to the coating and open end should be covered with polyethylene sheeting.

Each length of pipe shall be examined to make sure it is free from internal obstructions and shall be air blown to remove dust and sand immediately prior to erection or welding.

Materials released for the specific ISO shall be used for the specific ISO and can not be used elsewhere.

Scrap Materials shall be sent back to LOD with punched line number, heat no and material code.

Materials shall be received, stored, and delivered under code Material receiving, Handling, storing and Deliver.

Material Traceability

Identification code or File number shall be clearly marked on each plate, pipe and nozzle item by the Material Controller/Storekeeper.

QC personnel shall monitor the transferring of heat number for Stainless Steel material.

To prevent loss of traceability during paint/coating process, QC personnel shall make sure that the identification number is transferred to the QC record prior to blasting.

Piece marks and weld identification number shall be marked on each pipe/plate by suitable paint which shall be compatible with the base material to be marked and recorded on the relevant documents.

The heat number shall be transferred before the plate or pipe is cut.

Color-coding shall be applied for easy identification to permit quick material handling/segregation and visual check /monitoring during construction phrases.

Material Quality Control Material Traceability shall be in reference with (qcm number).

Pre Fabrication Activities

Checklist for Pre-Fabrication of Piping.

Approval of Method Statement, Quality Plan and ITP.

Approval of WPS covering all the material specifications.

Welder qualification list review and approval.

All the required Engineering drawings(approved) and documents are received in time.

All personnel and procedures for NDT, PWHT are approved.

Spool drawings marking field and shop weld joints shall be prepared, numbered and reviewed.

All tools, equipment and temporary items like pipe stands, pipe clamps etc., are ready in sufficient quantities.

Consumables shall arrange in sufficient quantities as per the WPS.

Welding data base set up prior start of welding activities.

Procedure for handling and storage of consumables shall be issued.

Isometric Mark-Up

All lines shall be clearly marked to easily identify the flow direction, service, line designation number, size, class and specification.

The Isometric drawing shall be used as a weld mark-up format.

Weld map shall be unique and separate for each line, system, component or assembly number.

The line diagram shall include weld location, weld numbers, tie point location, piece numbers and weld type, including: Field weld, shop weld, tie point, butt joint, socket joint, fillet weld.

Straight run of pipe shall contain the minimum number of welds. The use of off-cuts in straight run shall be avoided.

Joints before connection to the rotating equipment nozzles and its break up point shall be field measured and welded to avoid external loading on the equipment connection.

Piping butt welds shall be spaced a minimum one diameter as the run pipe or four times the thinnest wall thickness measuring between the heat affected zones, whichever is greatest.

Care shall be taken to ensure that the longitudinal welds clear branch connections.

Weld numbering methodology shall contain: a sequential number, a repair sequence number when applicable.

Length, height and width of the spools shall be within the limits of road transport and erection possibility, unless specifically requested.

Modification of pipe joint shall be done at site if necessary to avoid interference in accordance with the engineering clarification.

Cutting and Beveling

All pipes and fittings shall be cleaned before prefabrication by air blowing. In addition, for large diameters pipe rag cleaning should be conducted if found practical.

Proper safety procedure shall follow before starting the job.

Pre-fabrication of Stainless Steel and alloy piping shall be done in separate fabrication bays.

Marking should be done as per Isometric spool number measurement.

Cutting of pipes, fittings and edge preparation as per the drawing and WPS.

Based on spool breakdown of piping isometrics, pipe length shall be cut.

Extra length for pipe shall be provided in spools for field adjustment.

Pipes shall cut using Oxy-acetylene cutting or plasma as per project requirement.

Flame cutting of Stainless Steel is not allowed.

Stainless steel shall be cut with Stainless Steel cutting disc.

The edge cleaning and beveling shall be done using abrasive grinding disc.

Edge to be welded shall be prepared to meet the joint design requirements by any of the following method recommended:

Carbon Steel (C.S): Gas cutting, Machining or grinding methods shall be used. After gas cutting, oxides shall be smoothened/removed by chipping and grinding.

Alloy Steel: Gas Cutting, Machining or grinding methods shall be used. After gas cutting, machining or grinding shall be carried out on the cut surface.

Stainless Steels (S.S), Nickel Alloys: Machining or grinding methods shall be used. After cutting, cut surface shall be machined or ground smooth.

Where, spectacle plate is required by the ISO drawing, the fabricator shall drill a tap and install jack screw for flanges.

Heat numbers has to be transferred to pipes after cutting; remaining material must keep allocated locations with all marked specifications.

Electrical power source should be used for hand machine during fabrication.

Fit-Up and Track Welding

Fit-up assembly and joint alignment shall be carried out, by using couplers or clamps. All the required pipe holding work benches, assembling brackets, ‘U’ bolts etc. would be made to suit the pipe sizes.

For butt welds a uniform root gap shall be maintained as per WPS.

For all socket weld joints the pipe end shall be maximum of 3mm and minimum of 1.5mm.

All welding ends shall be beveled with an angle of 35°,±5°,and a root face of 1.6mm.

Welding end plane shall be normal to pipe axis as defined in the piping drawing, within 0.25°.

The inside misalignment shall not exceed 1.5mm (1/16”).

The maximum tolerance for axial dimensions, face-to-face, centre-to-face and locations of attachment shall be ±3mm.

Lateral transition of branches and connections from centerline of the run shall not exceed ±1.6mm.

Internal misalignment shall be limited to 1.6mm for pipe up to 24”, 3.2mm for pipe diameter 26” and above.

Seam orientation of welded straight pipe and pipe to fittings shall be in such a way that, circumferential angle between seam is at an angle of 30°.

Branches joint, connecting to the header line including reinforcement pad shall be pre-fabricated in the shop to avoid difficulties in site.

The pipes shall be tack-welded in equidistant positions to avoid cracking and bending or joint during welding. Tack weld shall be done by a qualified welder as per approved WPS.

In case of pipes with different thickness, the larger thickness shall be tapered in compliance with standard to match smaller thickness.

Line numbers, sheet numbers, spool numbers, material code and joint numbers are to be clearly marked on the spools with the welder identification for each joint.

Branch Connections

Branch connection requirements shall be in accordance with Project Specifications.

The lateral offset of branches and connections from the centerline of run shall not exceed ±1.6mm.

All welded branch connection and other joints shall be full strength reinforced as indicated on the drawings.

Reinforcement material shall be made from the same pipe material as specified by the relevant piping class and subject to the same specification requirements as the piping which is attached.

All cuts shall be carefully beveled and accurately matched to form a suitable preparation for welding and to permit full penetration of welds between the branch and the run pipe at all points.

All reinforcing pads shall have a minimum outer radius of 51mm, a 3-6mm deep hole shall be provided for each reinforcing pad.

Branch connections, vent nozzles, trunnions and other attachments including reinforcing pads shall not be welded over or near longitudinal or circumferential welds in the piping.

Longitudinal or circumferential weld to the next weld shall be 50mm measured between the heat affected zones.

For reinforcing pads, the minimum distance measured between the Heat Affected Zones of the weld in the pipe and fillet weld of the pad shall be 25mm.

Flange Connections

Unless otherwise indicated on the drawings, the bolt holes of all flanges shall be offset to vertical and horizontal centre lines.

The maximum angular deviation of bolt holes shall not exceed 1.5mm measured across the bolt pitch circle.

Flange faces shall be square to the pipeline in which they are fitted.

The fit-up of pipe ends and weld neck flanges shall be done to obtain uniform root opening. The criteria given in related WPS shall be followed.

Cleaning of spools

All pipes shall be internally cleaned by air blowing.

In addition, for large diameters pipes rag cleaning should be conducted if found practical.

All prefabricated pipe spools shall be visually inspected for cleanliness, and shall have foreign material removed from the inside.

The piping ends shall be covered after inspection to prevent unauthorized removal of the end cover prior to making the joint to the making to the succeeding section of piping.

During assembly and erection, the construction agency shall ensure that no foreign materials (such as welding consumables, lumbers, gloves, etc.) are left inside the piping system.

After assembly and installation, the piping shall be cleaned inside to remove all loose material. The cleanliness shall be verified visually inspection techniques.

PIPING ERECTION

All lifting tools, equipment’s and ropes used for erection shall be inspected and certified by HSE regulations.

Activities shall be done according to the proper method statement for lifting and handling.

Pre-fabricated spools shall be shifted to site carefully; care shall be taken while handling and stacking of spools to prevent any possible damage.

The Pre-fabricated spools shall be identified by spool and line numbers before erection.

Before erection of spools ensure for inside cleaning of the spools and their items.

The pre-fabricated supports shall be installed as per drawings, the pipe supports details shall be followed in the piping layout drawings and Isometric drawings for location and supports detail drawing.

All pipe openings shall be sealed before, during and after erection to prevent the ingress of moisture and foreign matter.

Threaded ends shall be plugged and sealed by waterproof grease tape or purpose made plastic caps or plugs. End cap or cover shall be placed on the open valve ends.

Erection of spools shall be carried out area by area as per piping layout drawings and Isometric drawings.

Approved and safe scaffolding and temporary platforms shall be arranged to carry out erection, fit-up and welding of field joints at elevated positions.

Erect the spools in position using crane or other lifting devices as per the drawings.

Shifting of pipe spool on pipe racks should be done on the roller support if required.

Piping installation on pipe rack shall be from lower level to higher level.

Large bore random length shall be installed, which is followed by small bore field run pipe. The sequence of composite spool will be same as of random length.

Joints shall be aligned and complete the fit-up/welding as per applicable WPS, Isometric drawing and Project specifications.

NDT and other inspection shall be completed for the field joints and recorded properly.

The final correction and modifications made to fabricate spool in order to allow for stress free installation, which should include; adjustment to pipe support, adjustment of flanges where free spaces are available in bolt holes, cutting and re-welding or introduction of additional field joints or fit-up pieces.

Pipe Supports Fabrication and Installation

Fabrication and installation of all pipe supports, hangers, guides and other support attachments shall be done in accordance with the details in the IFC drawings.

Welding preparations for the pipe to pipe supports and structural steel welding for pipe supports shall be in accordance with the corresponding WPS.

All pipe support shall be individually identified by number and this number shall be marked on the piping layout plans.

A 6mm weep hole shall be drilled for dummy supports and shall be located near the base plate for all vertical dummy supports, and near the run pipe at 6 o’ clock position for all horizontal dummy supports.

Flange Connections

All flanged connections shall be made using fully threaded stud bolts and nuts. A minimum of one complete thread shall protrude from the nut after completion of tightening.

The alignment of flanges to rotating and static equipment’s, the requirement shall be in accordance to client specification.

Temporary gaskets shall be identified by color coding on their handles exposed.

All bolt heads shall be assembled from the same side. A logical sequence of Bolt tightening shall be followed.

Special attention shall be given to ensure that in line items such as orifice flanges, spectacle blinds, valves, strainers etc. are installed and oriented correctly as indicated on isometrics and drawings.

Flange bolt holes shall be oriented as follows, unless otherwise indicated on the construction drawings:

Flange face vertical-Bolt holes to straddle vertical centerlines.

Flange face horizontal-Bolt holes to straddle horizontal centerlines.

Rotation of flanges-Offset between elevations of bolt holes on opposite sides of a flange centerline shall not exceed ±1.5mm.

DIMENSIONAL CHECKING

The fabricated piping shall be checked with IFC Drawing and Standard specifications for the following parameters.

Fit-up tolerances for length, depth, orientation and straightness of piping members.

Limits for spacing between pipe and supports.

Supports base plate elevation and degree of levelness.

Piping elevation and degree of levelness or slope.

Alignment of piping weld edges conforms to the WPS and specifications.

WELDING PROCEDURE

This section specifies the welding, heat treatment, Nondestructive Testing (NDT), and hardness testing requirements for welding pipelined and related equipment’s to ASME 31.1 and ASME 31.3, API STD 1104 and ASME SEC IX.

Codes and Standards

Welding Procedure

Before starting welding, the assigned people must wear proper PPE and adequate safety procedure must be implemented.

All welding electrodes shall be kept in required condition in both storage and welding.

The ends to be welded shall be properly cleaned to remove paint, oil, grease, rust, oxides, sand, earth and other foreign matter.

All ends shall be completely dry before the welding.

On completion of each run, craters, welding irregularities, slag etc., shall be removed by the grinding and chiseling.

Separate grinding wheels and wire brushes should be used for carbon Steels & Stainless Steel.

Welding face shall be prepared in such a way that, the face must be cut and grind smoothly and the imperfections (slots, spatters, surface oxide due to cutting and rusting) shall be removed from the welding area.

The Welding work piece shall be shielded against high winds and rain.

For the fabrication & Welding of Stainless Steel pipes, only Stainless Steel tools & consumables (Wire Brush Chipping, Hammer, and Abrasive disc) shall be used.

The pipeline joints shall be aligned as accurately as possible and the pipe must be supported properly to avoid bending and displacement during welding.

Fit-up joint shall be welded after checked by the QC inspector for acceptance and registered.

All branch connections shall be joined to headers with full penetration welding.

The bore side shall be ground smooth, free from cracks.

Welding shall be done as per approved WPS for the particular piping.

Pre-heating and welding consumable shall be checked before starting of welding.

Each weld layer shall be cleaned before starting to weld next layer.

The cleaned area shall be free from slag. Any visual defects like cracks, pores, spatters weld shall be removed by grinding before the next layer is applied.

Ends of weld layer shall be removed by grinding before the next layer is applied.

The ends of weld layer shall be removed by grinding at take-up points of each weld.

Appearance of finished weld shall be as even as possible and free from spatter, under cut, cracks, excess reinforcement etc. with reference to ASME b 31.3 and relevant WPS.

All parts that may be affected by the welding operations, such as accessories, insulation joints and such, shall be adequately protected.

For flange to pipe connections if welding shrinkage can lead misalignment, two similar flanges shall be joined by inserting a temporary gasket and then welded.

In Case of threaded pipes, screw threads shall be concentric with axis pipe with no blur or stripping.

The threading dies shall be sharp and properly designed for the piping material.

Proper tape/sealant for threaded joint shall be used as per project specification.

Pre-Heating

Preheat for the various grades of materials shall be in accordance with the specified Welding Procedures and Specifications.

Temperature-indicating crayons, thermocouples, or calibrated contact pyrometers shall be used to measure preheat and interpass temperatures.

The Preheat temperature shall be established over a minimum distance of 75mm on each side of the weld.

Post Weld Heat Treatment

If PWHT is applicable for any piping system, PWHT procedure will be applicable strictly.

The PWHT table shall include the following information for each joint or component: location, drawing number, diameter, wall thickness, material, heating rate, and cooling rate, soak temperature, and soak time.

Thermocouples and temperature recorders shall be calibrated and checked periodically.

All machined surfaces shall be protected from oxidation during the heat treatment by insulated by suitable coating material.

Production Weld Hardness Testing

Hardness testing of production welds is only required if specified.

The hardness indentations shall be made at or near the middle of the deposited weld bead and HAZ if specified.

If any reading exceeds the specified limit by no more than 10BHN, then minimum of three additional indentations shall be made near the original high reading.

GALVANIZING, PAINTING AND COATING

Painting shall not start before the acceptance of testing. It must be in accordance with relevant client specification for painting of piping line.

Appropriate personal protection and protective equipment is required in certain areas and when performing particular task.

All paints, coatings and thinners shall be stored in enclosed storage areas that are well ventilated and protected from temperature exceeding manufacture’s recommendations, open flames, electrical discharge and direct sunlight.

All electrical, Blast cleaning and spray painting guns shall be earthed (spark proofing) to prevent up of an electrostatic charges, especially when the application is in confined work places.

Welded areas shall be insulated before application of paint/coating for the field joint inspection during hydrostatic testing.

All mechanical operations, such as welding and drilling, shall be done before painting and galvanizing.

Procedure must cover the requirements governing the selection and application of the coating system to be applied on painting of, Piping, Pipe support, Structural Steel Electrical and Instrumentation Items as per the Client’s Specification.

All materials identification tags/markings shall maintain correctly during the all procedure to eliminate the misplacing of material during storage and construction.

Recorded approval of all items at each stage of surface preparation and coating application.

Abrasive Blast Cleaning (or) Power Tool Cleaning

Suitable cleaning methods can be adopted for removing mill scale, rust and other surface contaminations to achieve specified prescribed surface quality as per Client’s Specification.

Blast Cleaning shall not commence unless a protective coating can be applied before contamination or flash rusting occurs and the temperature are 3°C above ambient air dew point.

Stainless steel surface shall be blast cleaned by using suitable non-metallic abrasive such as aluminium oxide or stainless steels tools all free from halides, Sulphur and low melting point metals.

Before application of coatings the surface shall be cleaned to remove dust and abrasives by suitable method.

Galvanizing

Galvanized piping, structural steel components shall be specified for the specified service in the Client’s Specification.

Repair of damages shall be according to the applicable industry standards and codes.

Painting and Coating

The material used for coating and painting shall be specified for the specified service in Client’s Specification.

Coating/Painting components shall be power stirred well before application.

The coating thickness shall be uniform all over the area of application as per requirement.

Priming coating shall be applied as soon as possible after the surface preparations has been carried out.

Specified subsequent coat shall be applied after the primer coat has been carried out.

Each coat shall be allowed to cure thoroughly as per the coating requirements.

Coating shall only be applied when suitable weather conditions prevail(shall not apply temperature below 10°C, relative humidity exceeds 85%, steel temperature less than 3°C above the dew point, foggy/rainy/dusty conditions)

Coated items shall not be handled or moved until all coating have been properly dried or cured.

The coated items shall be loaded, padded, and secured for transport in such a manner that the coating will not be damaged.

IDENTIFICATION AND MARKING

All pipes and fabricated fittings shall be marked on their outside with letters and numbers defining their respective location and duties.

Marking shall be stamped, stenciled, tagged or otherwise clearly marked with permanent marking method.

During sand blasting, painting and galvanizing, the marking shall be masked and secured.

Material identification shall be maintained throughout the fabrication, installation and up to final inspection.

QUALITY ASSURANCE AND QUALITY CONTROL

The criteria of Quality Inspection will be in accordance with Project General Specification for different piping systems.

Inspection records shall be properly recorded and maintained with proper identification for each welded joint.

Inspection shall be carried out as per approved procedure and the results shall be recorded properly.

Safety procedures shall be strictly followed in each inspection procedure, in handling the inspection equipment’s and work environment.

Non-Destructive Testing (NDT)

The criteria of NDT will be in accordance with Client’s Specification for different piping systems.

The acceptance criteria shall be in accordance with ASME B 31.3, B 31.1 & SEC V,SEC VIII.

Welding and NDT records shall be properly recorded and maintained with proper identification for each welded joint.

NDT shall be carried out as per approved procedure and the results shall be recorded properly.

Surface irregularities including weld reinforcement, inhibiting accurate interpretation of specified method of NDT shall be ground smooth.

Safety procedures shall be strictly followed in each NDT procedure, in handling the NDT equipment’s and work environment.

PRESSURE TESTING

Identify the test loops for the completed line system wise.

Test packages shall be prepared with all welding/NDT summary, P&ID marked with Test limits, Isometric drawings, support details etc. for the completed lines of the system and submitted for Client’s approval.

The Test Pack documentation shall contain isometrics or relevant pack of pipe work related to package of piping system that is bearing tested and shall include following information:

Inside of all pipes, valves, fittings and other associated equipment are clean and free from loose foreign matter prior to commencement of the pressure test.

Upon obtaining mechanical clearance and test packages approval, Hydrostatic test shall be carried out as per project specification.

Test Package shall be prepared as per method statement and procedures.

Reinforcing pads shall be tested with clean and dry oil free air for the weld surfaces on the inside and outside shall be swabbed with a leak testing solution.

In-line instruments, control valves, manual block valves, special items, etc. that may interfere with a proper test or might be damaged during test, shall be not be installed before pressure test for fit-up and, or shall be removed for the test and substituted with temporary spools.

Temporary test gaskets shall be installed for the test on location with temporary blinds or spools.

However permanent gaskets may be used for the flanged joints which will remain unopened during and after pressure test.

Screwed tapping, for example in orifice flange sets, shall be plugged.

Non-return valves, if installed, will require that the piping network be pressurized from the upstream side.

High point vents to release air from the system whilst filling with the test medium and low point drains, either valve or plugged.

Two pressure gauges (minimum) shall be used for the test.

The gauges shall be calibrated and certificate attached to test package before pressure test.

Maximum range of gauge will be 1.5 to 4 times of test pressure.

Once the pressure of the line is stable, inspection of the line shall commence.

The test pressure for process or power pipe shall be for a minimum of 30 minutes or as required to inspect the line.

In case of leakage, the line shall be retested after repair according to the related procedure.

When the test has been successfully completed, lines are de-pressurized by operating vent valves gradually.

Then the complete discharging of the system through the drain valves is taken up, keeping the vent valves always open. The line shall be de pressurized and drained completely.

All test blinds shall be removed and the line shall be reinstated with permanent gaskets.

Hydrostatic test shall be followed under code: Hydrostatic test procedure of piping.

FLUSHING

After completion and approval of hydrostatic testing of the system, all lines and equipment’s shall be drained and flushed.

Special attention shall be given to points where water and sediments may be trapped, such as valve bodies or low points.

A circulation loop may be established and the system flushed until circulating water is clear.

Piping completed the pressure Testing shall be internally cleaned to remove all remaining foreign matter by water flushing or blowing with air.

Piping and equipment shall be dried and all traces shall be removed as per Client’s Specifications.

Where special condition exist such as cleaning compressor section and oil lube piping, separate cleaning method shall be adopted as per the Vendor’s or Owner’s specifications.

RE-INSTATEMENT

After successful completion of pressure testing, flushing and draining, the system shall be returned to a state of commissioning readiness as per drawing specifications and requirement.

All temporary materials such as spades, blinds, gaskets and temporary supports should be removed from the system.

Spectacle blinds should be repositioned to the correct position as per the P&ID.

All accessible points of the system shall be inspect to ensure that it is free of scale, rust, loose paint and film and is of correct surface appearance.

Nitrogen blanket shall be re-established for specified critical components or systems in accordance with manufacturer’s instructions and project procedures’.

All items those were removed from the system before hydro test such as control valves, inline instruments etc. should be re installed after hydro test and flushing.

Punch items should be removed and all test vents should be seal welded.

All competed system should be inspected for the correct flow direction in piping and instruments.

Exit mobile version