Diesel Generator DG Set Installation Method Statement

TABLE OF CONTENTS

SCOPE

This procedure is developed for safe and secure supply and installations of diesel generator set for any kind of the project, document details diesel generator installation including:

DEFINITIONS

PQP: Project Quality Plan

PSP: Project Safety Plan

QCP: Quality Control Procedure

HSE: Health, Safety and Environment

MS: Method Statement

ITP: Inspection Test Plan

QA/QC: Quality Assurance / Quality Control Engineer

WIR: Inspection and Test Request

MIR: Material Verification Record

HEALTH AND SAFETY

Strictly follow as per the manufacturer’s Health and Safety recommendations for handling and use of the materials.

Ensure all involved personnel shall be aware of the same.

Specific safety measures have to follow as applicable, and all the safety measures are covered separately in the project safety plan.

Material Handling and Storage

Material used will be as approved by the Engineer.

The sizes and routes routing will be as per the approved Shop Drawings.

Deliver components parts to site, completely identified in accordance with shop and certified CAD Drawings prepared for this work.

Store in accordance with the manufacturer’s instructions, above ground, properly protected from the weather and construction activities.

INSTALLATION AND FIXATION

Off-Loading:

Use Mobile Crane to off-load the Generator Sets.

Capacity of crane shall be capable to carry the weight of the generator set.

All safety precaution shall be adhered during off loading.

Ensure the safety of equipment’s and workers all the time.

Off load the Generator sets on the designated off loading area.

Make sure that the Generator Set will seat on pipe rollers or wooden planks.

If the Generator Room is not ready for generator set installation, proper protection of Generator set shall be provided and cover it suitably.

Pre-Installation:

All materials and documentation relevant to this particular section of works shall be checked prior to the installation.

Make sure that the plinth is completed and painted and ready for final installation of equipment.

Make sure that the generator room is clear and free of debris and foreign materials.

Ensure that the access for generator set installation is free from obstructions.

Make sure that supporting flanks, pipe rollers, chain blocks, hydraulic jacks and other tools required for installation are in place.

Diesel Generator Installation Steps:

Lift the Generator using mobile crane or portable hydraulic crocodile jack. Place pipe rollers under the generator skid.

Make sure that the pipe rollers are properly set.

Once the generator set will sit on the pipe rollers, push in / pull in the generator set inside the room.

If required, use chain block to pull the generator set.

Make sure that the chain block is properly anchored and properly set to the direction of generator position.

Where in a generator set crosses a trench or unequal elevation, use steel channels or I- beams to support the pipe rollers.

Make sure that the steel channels or I-beams are properly supported to carry the weight of the Generator set.

Set the Generator set in proper location.

Lift the Generator set using portable crocodile hydraulic jack and let it sit on elevated planks or I- beams.

Fix the spring vibration isolator. Ensure that it is fixed and aligned properly.

Lift the Generator set and install the spring vibration isolator.

Bolt and tight properly the Generator base on to the spring vibration isolators.

Associated work related to the Generator set such as generator exhaust system, fuel system, acoustic lining etc, will commence.

After completing all associated works related to the Generator set, raise a Request for Inspection for Generator Installation.

Commissioning:

Test the generator in accordance to specification and manufacturer recommendations.

All testing will be carried out in the presence of consultant and manufacturer/ supplier.

Test shall be carried out by the manufacturer’s testing engineers.

All test sheet shall be certified by the manufacturer representative.

Technical Assistance:

The installation supervising technician for the system trade shall instruct the consultant, and construction site manager on the programming and correct operation of the system after the installation is complete.

This instruction shall be scheduled at the convenience of the staff.

All such instruction shall be properly recorded.

WIR will be issued for consultant approval upon making sure that the installation of the system equipment’s is done as per approved shop drawings, specifications and manufacturer recommendations.

ROLES AND RESPONSIBILITIES

PROJECT MANAGER

SITE ENGINEER

FOREMAN

SAFETY ENGINEER

TECHNICIAN FROM DIESEL GENERATOR SUPPILER

The carrying-out of work and the proper distribution of all the available resources in coordination with the subcontractor Site Engineer on daily basis.

Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.

Complying with the sub-contractor basic design practices, particularly those related to safety and engineering

Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.

STORE KEEPER

Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.

One who will acknowledge the receiving of materials at site in coordination with QA/QC and concerned Engineer.

MANPOWER REQUIRED

Charge hand, Experienced Technicians, labor, riggers, and operators etc.

MATERIALS REQUIREMENTS

Diesel Generator Components and Accessories

EQUIPMENTS REQUIREMENTS

Necessary equipment for diesel generator installation will be as follows:

P.P.E. – Personal Protective Equipment

(safety helmet, Boots, gloves & safety vest )

WASTE MANAGEMENT

The Rubbish which would be created from our scope of works will be disposed to the designated dumping ground.

SPECIAL CONTROL MEASURES

The following general control measures against Safety, Environment and Quality shall be required for the scope of work and special control measures are not applicable:

Proper PPE must be worn at all timePermit to work at height > 2m where applicableLifting operation permit (using crane) where applicable.

Confined space permit where applicable.Approved work method statement and risk assessment will be made available to site.

All workers doing the work shall be briefed on this method statement and risk assessment.

SUPPORTING DOCUMENTATION

This method Statement should be read in conjunction with the below referenced documentations:

DISTRIBUTION

Copy of this method statement shall be issued to the following for information / action / comments:

 