Below is detailed risk assessment and job safety analysis for testing and commissioning of booster pumps.
Risk Assessment will be reviewed and updated based on site conditions and after any major incident.
The most common form of risk assessment is to examine a hazard and possible consequences of exposure to that hazard and the likelihood of that particular Impact / consequence eventuating.
This risk assessment result is called as risk level.
By using Risk Assessment Matrix evaluate the quantitative risk analysis where numerical data is used.
Risk Rating:
1 – 3 Low
4 – 6 Moderate
8 – 12 High
15 – 25 Extremely High
I-Impact,
L- Likelihood,
RS-Risk Score
| S. No. | Identify Task
Think about the work area each stage of the work to be performed
|
Identify Hazards
Against each stage / item list the hazards that could cause injury / incident when performed |
Risk / Consequences | Persons at Risk | Initial Risk Rating | Risk Control Measures
Control measures required to eliminate or minimize the risk |
Residual Risk Score | Responsible | ||||
| L | I | RR | L | I | RR | |||||||
| 1 | Pre/Post worksite arrangements | Poor site conditions
Un-authorized personnel Slip trip and fall Poor access/egress |
Injury to Operatives
Property Damage |
Operatives
Staff Visitors
|
3 | 3 | 9 | Ø Obtain valid permit(entry) before the commencement of the activity.
Ø All the personnel involved shall be HSE Inducted Ø Only authorized and competent operative shall be involved in the activity Ø Area to be inspected initially and any issues to be highlighted Ø Shall follow proper instructions from supervisor Ø Work area shall be barricaded if necessary Ø Access/egress need to be ensured initially Ø Proper housekeeping shall be ensured. Ø Ensure proper PPE shall be follow. |
1 | 3 | 3 | Project Engineer/
HSE/ Site Supervisor |
| 2 | Use of hand tools and during the testing activities | Improper tools
Damaged or modified tools Flying particles Electricity Electrical Shock Noise Vibration Dust Rotating Parts Injury
|
Injury to Operatives
Property Damage Electrocution
|
Operatives
Staff Visitors
|
4 | 3 | 12 | Ø Ensure Use of hand tools and its hazards to be discussed in the daily TBM.
Ø Right tool should be used for the job. Ø Tools must be in good condition. Ø All the power tools shall be inspected and color-coded prior to the usage. Ø No damaged tools shall be used and it should be discarded. Ø No modifications tools are not allowed. Ø All the hand tools should be inspected prior to its use by the user. Ø Tools must be double insulated and inspected daily. Ø Any damage of the tool to be reported to immediate supervisor. Ø After completion of the job tools shall be stored in the designated storage locations. Ø Ensure proper PPE shall be followed. Ø HSSE Guidelines shall be followed where ever applicable |
1 | 3 | 3 | Site Supervisor
|
| 3 | Manual handling of materials during the preparation and Maintenance | Ergonomic issues
Improper posture Twisting of body Heavy load Irregular shape of load Poor floor conditions (Slip, trip and fall) Sharp edges Walkways obstructed Lack of proper illumination Musculoskeletal disorders Hand/Foot Injuries
|
Injury to Operatives
Property Damage |
Operatives
Staff Visitors
|
4 | 3 | 12 | Ø Manual handling- hazards and control measures to be discussed in the TBM
Ø More personnel to be deployed for shifting heavy loads (One person= 20Kg Max) Ø If possible, to split the heavy loads, then proceed with that Ø Mechanical aids like wheelbarrow, jack trolley shall be provided Ø Ensure that the floor condition is good and not slippery Ø All the personnel involved shall be provided with in-house training for manual handling. Ø Proper supervision shall be ensured Ø Sufficient illumination shall be ensured for walkways, entrance and exits Ø All the walkways, entrances and exit shall be clear without any obstructions. Ø Ensure Proper use of appropriate PPE |
1 | 3 | 3 | Site Supervisor |
| 4 | Visual inspection of components. | No proper isolation of power
Electricity In competent personnel Slip trip and fall Exposed cables
|
Injury to Operatives
Property Damage
|
Operatives
Staff Visitors |
4 | 3 | 12
|
Ø Ensure that area is declared start prior to the start of the T&C.
Ø Applying work permit, lockout/tag out procedure & isolation if applicable. Ø All the personnel shall be competent to do the task Ø Do not wear jewelry or loose clothes during the task Ø Proper supervision shall be ensured Ø Proper use of PPE shall be ensured during the activity Ø Proper Illumination. |
1 | 3 | 3 | Site Supervisor / foreman |
| 5 | Testing and commissioning
Operation of Booster pump, Heat Pump & Circulation pump |
Electrocution
Failure of testing. Slippery floors Noise Short Circuit Fire |
Injury to Operatives
Property Damage |
Operatives
Staff Visitors |
4 | 3 | 12 | Ø Ensure PTW shall be follow (ENERGIZATION & LOTO)
Ø Proper supervision required. Ø Ensure lockout & tag out procedure if required. Ø All testing tools must be certified and calibrated. Ø Barricade with proper signage and safety warning. Ø Required safety equipment’s to be used in DBs (e.g. Breakers, ELCB). Applying work permit, lockout/tag out procedure & isolation Ø Pumps connected to the general mass of earth in such a manner as to ensure an immediate safe discharge of electrical energy. Ø Wear adequate PPE at work. Ø HSSE Guidelines shall be followed where ever applicable. Ø Proper handover shifts in place. Ø Proper illumination at work. |
1 | 3 | 3 | Project Engineer / QA-QC Engineer / Supervisor/ Foreman |
| 6 | Working at Height/ Podium Ladder
(nonconductive) |
Falling from height.
Falling objects Improper use of ladder Loose materials Fall, slip & trip hazard Poor visibility Incompetent persons Lack of training Poor housekeeping Not following safe work procedure |
Serious Injury
Personal Injury Property damage |
Scaffolders
Workers Visitors Supervisors |
4 | 5 | 20 | Ø PTW system to need to be implemented.
Ø All personnel working 1.8 meters or above to wear Safety Harness and practice 100% Tie off. Ø Specific training shall be provided. Ø Strict monitoring and supervision. Ø Ensure the safety harness inspected and color coded. Ø All ladders used to be in the fiberglass or nonconductive as per standard. Ø Ensure area is barricaded where work is conducted at height Ø Ladder shall be inspected and color coded. Ø Highest standard of housekeeping to be observed on top of scaffolds Ø All mandatory PPES to be worn. Ø HSSE Guidelines shall be followed where ever applicable |
1 | 5 | 5 | Site Engineer / Supervisor / Foreman / Scaffold Inspector |
| 8 | Testing with Multi meter. | Electric shock
Unauthorized/ untrained Person Faulty Instrument Improper identification Electricity |
Injury to Operatives
Property Damage Fatality |
Operatives
Staff
|
4 | 3 | 12 | Ø Trained person only to do the megger testing.
Ø Ensure testing kit calibrated with third party inspection sticker Ø Provide project color code. Ø Proper Supervision. Ø Provided warning boards and Barricaded. Ø Ensure adequate PPE shall be worn. Ø HSSE Guidelines shall be followed where ever applicable |
1 | 3 | 3 | Project Engineer / QA-QC Engineer / Supervisor/ Foreman |
| 9 | Working with Electricity | Electricity
Conductors Broken wires Improper plugs Overloading |
Injury to Operatives
Property Damage |
Operatives
Staff Visitors |
4 | 3 | 12 | Ø Only those persons who have been adequately trained and experienced in the work of electricity to allow for the same.
Ø Electrical work shall not carry out in wet conditions. Ø Do not overload to the circuits. Ø Communicate to all personnel about testing and commissioning. Ø Don’t use homemade electrical accessories and use industrial type. Ø Disconnect main supply before commencing of work. Ø Defective tools and equipment should not be used, report it and replaced it immediately. Ø Temporary power supply shall be taken through standards rated MCBs & RCDs. Ø Temporary power supply cable shall not have joints. Ø The working area is maintained dry and clean. Ø Barricade the location and signage to be placed where circuits and equipment’s are energized. Ø Maintain proper lighting and clear access route. Ø PPE should wear at all-time where working in energized circuits. Ø HSSE Guidelines shall be followed where ever applicable |
1 | 3 | 3 | Project Engineer / Supervisor/ Foreman |
| 11 | Work-at-Night (work at poorly
illuminated areas) |
Inadequate illumination / lighting
Poor housekeeping. Fatigue. |
Slips, trips, and falls.
Collision on stationary objects such as plant and equipment. Cuts and bruises due to collision on sharp objects. Collapse of personnel |
Drivers
Workers Operators Supervisor Pedestrians
|
3 | 3 | 9 | Ø Relevant PTW to be obtained prior to night activities.
Ø Night/ Dark area activities shall be carried out with strict monitoring and supervision. Ø Adequate lighting system as per approved value lux shall be provided on site during all night activities or on dark areas as per procedures. Ø Proper work rotation to be ensured (workers on day shift shall not be allowed in night shifts). Ø Proper housekeeping shall be maintained prior to commencement of night activities. Ø Ensure adequate rest periods for inspection teams and repair technicians. Ø Ensure that all personnel are well aware of emergency access / egress at site and adequate supervision. Ø Flash lights / Torches shall be provided on all exit routes. Ø All relevant PPE must be worn. Ø HSSE Guidelines shall be followed where ever applicable |
1 | 4 | 4 | Construction Manager /
HSE officer / Project engineer / Site Engineer / Supervisor |
| 11 | Access & Egress, Housekeeping | Slip hazards such as spilt liquids
Material stored on access routes. Tripping over loose objects on floors, stairs and platforms, trailing cables, damaged or uneven floor surfaces. Striking against projecting, poorly stacked items or misplaced material. Cutting, puncturing, or tearing the skin of hands or other parts of the body on projecting nails, wire or steel strapping |
Personnel Injury
Eye Hand or facial injury |
Drivers
Workers Operators Supervisor Pedestrians
|
4 | 3 | 12 | Ø Keep work areas tidy, particularly floor areas.
Ø Waste products, containers and materials must be cleared and tidied as work progresses Ø Do not allow cables to trail across access routes – tie them at high level if possible. Ø Proper cable management to be done. Arrange all cables overhead with wooden stand. Ø Clear up spillages as quickly as possible – put temporary barriers up if the spillage makes the floor surface slippery. Ø Don’t leave materials or equipment on pedestrian routes, staircases or blocking emergency exits. Ø Make sure access routes are adequately lit – this may require temporary lighting particularly in areas where floor levels change including stairways. Ø Ensure work area is free (as is practicable) from trailing cables, tools, materials, debris and spills. Ø Empty containers to dispose OFF separately. Ø All flammable materials to be removed from the area. Ø Work area to be inspected before leaving. Ø All work should be from a suitable and stable work platform Ø The use of ladders restricted to trained users and must be cleared with supervisor. Ø HSSE Guidelines shall be followed where ever applicable |
1 | 3 | 3 | Project Engineer / Supervisor / Foreman |
| 12 | Adverse weather condition
|
For, Heavy Fog, Rain
Sandstorm, Heavy wind Constantly working without drinking water, exposed to the sun Exhaustion, nausea, vomiting, dizziness, headaches, confusion, disorientation, heat stress, Heatstroke/cramp Heat stroke/heat stress/ muscle cramp neurological disorders, vascular musculoskeletal
|
Injury to Operatives
Property Damage.
|
Operatives
Drivers and operators Staff Visitors
|
4 | 3 | 12 | Hot Weather
Ø Strict monitoring and supervision. Ø Heat index chart and MOL regulation to be maintained and activities to be stopped when heat index indicates so. Ø Work-Rest balance to be ensured. Ø Personnel hydration to be consistently maintained. Ø Adequate rest and rotation to be implemented. Ø Activities to be scheduled according to weather conditions. Ø Weather monitoring chart to be monitored effectively. Ø Emergency procedures and preparedness to be communicated to all workers. Ø Additional mechanical ventilation to be provided at all times in work areas. Cold Weather Ø Personnel body temperature to be monitored. Ø Winter jackets to be provided if work is to be carried out in extreme cold Ø weather conditions. Ø Workers advised to take warm water when necessary. Ø Strict monitoring of health conditions of workers. Ø All activities shall be carried out in clear visibility. Ø If the presence of fog /mist deters visibility, all activities shall be halted until clear visibility is attained.
|
1 | 3 | 3 | Project Engineer / Supervisor / Foreman |
| 13 | Emergency preparedness and response | Fire
Explosion Electrocution Earthquake |
Fatality
Delay in evacuation Property damages |
Technicians
Helpers Operators Staff
|
4 | 5 | 20 | Ø Site specific emergency response team to be formed. Trained first aider, fire warden and fire fighter to be available in the ERT team and physically available at site.
Ø Emergency response training shall be conducted. Ø Emergency contact number shall be communicated with all employees at site. Ø Provision of adequate first aid, firefighting and spill response provision at site Ø Mock drill to be conducted. Ø Do not run, be calm, and walk towards nearest assembly Point during any emergency. Ø LIFE SAVING RULES to be communicated to everyone in the project. Ø No smoking policy shall be complied.
|
1 | 5 | 5 | Project Manager /
HSE LEAD / Project engineer / Site Engineer / Supervisor/ Foreman/ Charge hand |
