Site icon Method Statement HQ

Pipe Jacking Method Statement Using Automatic Tunneling Machine

The objective of this method statement is to define the installation sequence of casing pipe by means of Pipe Jacking using Herrenknecht Automatic Tunneling Machine with Slurry Material Removal (AVN machines).

Table of Content

Soil Investigation

Soil sample shall be taken and submit to approved laboratory for testing to decide whether pipe jacking is feasible. Trial pits are particularly useful in obtaining information on the uniformity, extent, ground water table and composition of soils. The Engineer s interpretation of the Soil Investigation report shall be provided along with any assumptions made.

Identification and Location of Existing Utilities

Location of utilities prior to any works is essential. All existing utilities shall be exposed.

Coordinates and levels of the utilities shall be recorded, Shop drawing shall be prepared to show existing utilities and proposed pipe jacking pipeline. It will then be submitted to required authorities to obtain relevant NOC(s).

Responsibilities

Project Manager

Project Engineer

QA/QC Engineer

Site Engineer

Safety officer

Materials

Material shall be procured as per project specification.

Casing Pipe with smooth walled with minimum yield strength of 36,000 psi (ASTM A1011)

Carrier pipe meet requirements to Dubai Municipality.

Grout.

Dielectric material.

Plant & Equipment

Labour Requirements

PPE List

HSE Requirements

Pipe Jacking Method Statement

Preparatory work

Pipe Jacking

Installation of Carrier Pipe

After casing pipe has been installed, the carrier pipe shall be laid to line and level.

Carrier pipe shall be supported on spiders clamped to the pipe or on flat bars welded across the steel sleeve.

Once all the carrier pipes are securely fixed in position and checked, a breather pipe will be placed at the soffit.

Then concrete/block work head walls shall be built at the end of the steel pipe.

Grouting

Prior to grouting the carrier pipe shall be filled with water and in case of uPVC this will be circulated to avoid damage due to the heat of hydration.

The annulus between the carrier pipe and the sleeve shall be filled with foam concrete (1000kg/ m3)

Foam concreting shall be continuous until sleeve is completely filled.

Grout Mix Design:

SRC: 432 kg

Dune Sand: 1214 kg

Water: 360 kg

Superplasticizer: 3 liter

Slump: Collapse

Backfilling

Backfilling will be carried out after inspections are done by all concern authorities and approved by them.

The thrust and reception pit shall be backfilled layer by layer in accordance to specifications.

After completion of backfilling, the original condition of the ground shall be re – instated.

Exit mobile version