Storm Drainage Water Piping Network Installation Method Statement

1. Purpose

The purpose of this method of statement is to define the safe and systematic procedure for the installation, testing, inspection, and commissioning of storm drainage water piping networks for construction projects.

By implementing this storm drainage water piping network method statement contractor shall ensure that all storm water drainage works are completed in accordance with:

The objective is to achieve a fully functional storm water drainage system capable of safely collecting and discharging rainwater and surface runoff without leakage, blockage, settlement, or structural failure.

2. Scope of Work

This method statement covers all activities related to storm water drainage piping systems including:

The procedure applies to underground storm drainage networks installed in any kind and size of residential, commercial, industrial, infrastructure, and utility projects.

3. References

The following standards and approved documents shall be referenced before commencement of work:

4. Responsibilities

4.1 Project Manager

The Project Manager shall:

4.2 Site Engineer

The Site Engineer shall:

4.3 QA/QC Engineer

The QA/QC Engineer shall:

4.4 Surveyor

The Surveyor shall:

4.5 HSE Officer

The HSE Officer shall:

5. Materials

Approved materials to be used for storm drainage installation that may include:

All materials shall be approved prior to delivery and installation on the project site area.

6. Tools and Equipment

The following equipment shall be available at site:

EquipmentPurpose
ExcavatorTrench excavation
Dewatering pumpsGroundwater control
Plate compactorsSoil compaction
Roller compactorBackfilling compaction
CranePipe lifting
Pipe laser levelAlignment and gradient
Total stationSurvey works
Concrete vibratorConcrete compaction
GeneratorPower supply
Water tankerTesting and curing
Hand toolsGeneral installation

All equipment shall be inspected and certified before use.

7. Health, Safety and Environmental Requirements

Prior to commencement of works, the following HSE requirements shall be implemented.

Safety Requirements

Mandatory PPE

All personnel shall wear:

Environmental Controls

8. Pre-Construction Activities

Before starting storm drainage installation works, the following shall be completed:

No excavation shall proceed without approval from the consultant and relevant authorities.

9. Survey and Setting Out

The surveyor shall establish the pipeline route based on approved shop drawings.

The following shall be verified:

Benchmarks and reference points shall be protected throughout the construction period as per the satisfaction of consultant/client.

10. Excavation Works

Excavation shall be carried out according to approved drawings and project specifications.

Excavation Procedure

  1. Mark excavation boundaries
  2. Install safety barriers
  3. Excavate trench to required depth only
  4. Maintain trench width as per pipe diameter as specified
  5. Remove unsuitable materials
  6. Keep trench dry and stable all the time

Where excavation exceeds safe depth limits, trench shoring or sloping shall be provided.

Excavated material shall be stockpiled away from trench edges to avoid collapse.

11. Dewatering Procedure

Where groundwater is encountered, dewatering shall be implemented before pipe installation.

Dewatering Activities

Continuous monitoring shall be conducted to ensure trench stability during installation activities.

12. Pipe Bedding Preparation

Pipe bedding shall be prepared according to approved specifications.

Bedding Requirements

Bedding material shall typically consist of approved granular material or sand.

13. Storm Drainage Pipe Installation Procedure

General Installation Requirements

Storm drainage pipes shall be installed starting from downstream toward upstream direction.

The following requirements shall be maintained:

Pipe Jointing

Jointing shall be carried out according to manufacturer recommendations and as per approved method statements.

Typical jointing methods include:

Make sure that all the lubricants and jointing materials are approved for specific applications.

14. GRP Pipe Installation Procedure

For GRP pipe installation:

Pipe joints shall be checked for proper seating before backfilling.

15. uPVC and HDPE Pipe Installation

uPVC and HDPE pipes shall be installed according to approved installation guidelines.

Installation Requirements

Pipe damage during installation shall not be permitted.

16. Concrete Encasement and Surround

Concrete encasement shall be provided where specified in approved drawings.

Concrete Works Procedure

  1. Install formwork if required
  2. Position pipe correctly
  3. Verify alignment and slope
  4. Pour approved concrete carefully
  5. Compact concrete using vibrator
  6. Protect pipe from movement during pouring

Concrete shall achieve required strength before further loading.

17. Manhole and Inspection Chamber Construction

Stormwater manholes and chambers shall be constructed as per approved structural details.

Construction Activities

Manholes shall be aligned with incoming and outgoing pipe inverts.

18. Testing of Storm Drainage Network

Testing shall be conducted after completion of installation works.

Hydrostatic / Water Test Procedure

The testing sequence shall include:

  1. Plug both ends of pipeline
  2. Fill pipeline with water slowly
  3. Release trapped air
  4. Apply specified test pressure
  5. Maintain pressure for specified duration
  6. Inspect joints for leakage

No visible leakage or unacceptable pressure loss shall be permitted.

19. Backfilling Procedure

Backfilling shall commence only after successful inspection and testing approval.

Backfilling Requirements

Warning tape shall be installed at specified depth before final backfilling.

Compaction testing shall be performed according to project specifications.

20. Inspection and Quality Control

The following inspections shall be conducted during the works:

Inspection ActivityResponsible
Excavation inspectionSite Engineer
Bedding inspectionQA/QC Engineer
Pipe alignment checkSurveyor
Joint inspectionQA/QC Inspector
Manhole inspectionConsultant
Testing inspectionConsultant / QAQC
Backfilling inspectionQA/QC Engineer

Inspection Request (IR) shall be submitted for each stage of work in compliance with the approved inspection and testing plan.

21. Acceptance Criteria

The storm drainage piping system shall be accepted when:

22. Common Drainage Pipe Installation Problems and Solutions

ProblemCauseCorrective Action
Pipe misalignmentImproper beddingReinstall and re-level
Leakage at jointsPoor jointingRejoint and retest
Pipe settlementInadequate compactionRecompact bedding
Water accumulationIncorrect slopeCorrect pipe gradient
Trench collapseWeak shoringReinforce trench support

23. Attachments

The following records shall be maintained:

All documentation shall be submitted for consultant approval during project handover.

24. Conclusion

The proper installation of storm drainage water piping networks is essential to ensure long-term system reliability, effective stormwater management, and protection of surrounding infrastructure.

By following this detailed method statement, the contractor can ensure safe execution, proper quality control, compliance with specifications, and successful completion of stormwater drainage works in accordance with approved engineering standards.