Below is a sample checklist for inspection of road works which you can use for doing the inspection of road works.
Stage of work/Item | Technical Parameters to be checked / ensured | As per estimate | At Site |
Geometrics (verify irrespective of stage of work) |
To check and ensure the following
a) Length |
||
b) Roadway width ( 6.00m/7.50m) | |||
c) Carriage way width (3.00m /3.75m) | |||
d) Shoulder width (1.875m /1.50m) | |||
e) CC pavement width | |||
f) Camber of shoulders and embankment ( Range- 4 to 5% in case of Earthen road, 3.5 % to 4% in case of Gravel/WBM surface and 3 to 3.5% in case of BT surface) |
Does not arise |
Yes |
|
No |
|||
Not adequately done | |||
Sub Base / GSB |
Thickness in “mm” |
||
Whether the compaction is adequate |
Does not arise |
Yes |
|
No |
|||
Not adequately
done |
|||
Whether Shoulder is compacted simultaneously along with the Sub base |
Does not arise |
Yes |
|
No |
|||
Not adequately done |
Stage of work/Item | Technical Parameters to be checked / ensured | As per estimate | At Site | ||||
Base course (WBM Gr II/III or WMM) |
Whether metal aggregates conform to required grading (in case of WBM construction)
Grading Requirement for WBM
Grading requirement for WMM |
Does not arise |
Yes |
||||
No |
|||||||
Sieve Size | Percent by mass
passing |
||||||
53.00 mm | 100 | ||||||
45.00 mm | 95-100 | ||||||
Not adequately done |
|||||||
26.50 mm | – | ||||||
22.40 mm | 60-80 | ||||||
11.20 mm | 40-60 | ||||||
4.75 mm | 25-40 | ||||||
2.36 mm | 15-30 | ||||||
600 micron | 8-22 | ||||||
75 micron | 0-8 | ||||||
Material finer than 425 micron shall have plasticity Index (PI) not exceeding 6 |
|
Stage of work/Item | Technical Parameters to be checked / ensured | As per estimate | At Site |
Whether the Volume of gravel is within 22% to 24% (in case of WBM construction) |
Does not arise |
Yes |
|
No |
|||
Base course (WBM Gr II/III or WMM) |
Not
adequately done |
||
Thickness (WBM/WMM)
WBM Gr.I – 100 mm |
Yes |
||
WBM Gr.II -75 mm | No | ||
WBM Gr.III -75 mm | Not adequately done |
||
Whether the compaction is adequate (Field density test) |
Does not arise |
Yes |
|
No |
|||
Not adequately done | |||
Whether Shoulder is compacted simultaneously along with the Base course |
Does not arise |
Yes |
|
No |
|||
Not adequately done | |||
Prime coat /Tack coat |
Whether WBM/WMM surface is properly cleaned before applying Prime coat/tack coat |
Does not arise |
Yes |
No |
|||
Not adequately done |
Stage of work/Item | Technical Parameters to be checked / ensured | As per estimate | At Site |
Prime coat /Tack coat |
Whether Prime coat/ tack coat is applied uniformly over the cleaned WBM/WMM surface before laying BT |
Does not arise |
Yes |
No | |||
Not adequately done | |||
Bituminous layer |
Thickness | ||
% of Binder content (Required – 4.32% , +/- 0.30%) |
Does not arise |
Yes |
|
No |
|||
Not adequately done | |||
Whether the compaction is adequate |
Does not arise |
Yes |
|
No |
|||
Not adequately done | |||
Road Furniture |
Whether Name Board is provided |
Does not arise |
Yes |
No |
|||
Not adequately
done |
|||
Whether KM stone and HM stone are properly fixed with concrete base |
Does not arise |
Yes |
|
No |
|||
Not adequately done |
Stage of work/Item | Technical Parameters to be checked / ensured | As per estimate | At Site |
Whether Sign board(s)/Cautionary Boards is provided |
Yes |
||
No |
|||
Not adequately done | |||
Shoulder |
Whether Gravel (or) excavated side earth (or) carted earth is provided for shoulder |
||
Drainage |
Whether Proper side drain is provided for avoiding stagnation of water along the road side |
Does not arise |
Yes |
No |
|||
Not adequately done | |||
Culverts |
Number and location of culvert(s) | ||
Whether the culvert(s) provided is adequate (or) necessary as per site condition |
Does not arise |
Yes |
|
No |
|||
Not adequately done | |||
Whether cross drain is properly integrated with the side drain |
Does not arise |
Yes |
|
No |
|||
Not adequately done |
Stage of work/Item | Technical Parameters to be checked / ensured | As per estimate | At Site |
Retaining wall |
Whether the retaining wall provided is adequate in required location(s) |
Does not arise |
Yes |
No |
|||
Not adequately done | |||
Preparation of Bill |
Whether bill is prepared without fail |
Does not arise |
Yes |
No |
|||
Payment |
Whether payment has been made upto the present stage |
Does not arise |
Yes |
No |
|||
Whether Final payment has been made (For completed work) |
Does not arise |
Yes |
|
No |