The purpose of below hvac method statement is to define steps for installation testing and commissioning of Air Handling Units AHU’s.
By following and implementing the below guidelines contractor shall ensure that the job execution complies with the project requirements and serves the intended function to satisfactory level of the client & end users.
Following Tools & Equipment’s shall be arranged:
- Fork Lift or Crane with capacity & arrangement in line with the Manufacturer’s recommendations
- Hydraulic Trolley
- Portable hand tools
- Portable Drilling Machine/ Grinding Machine & Angle Cutter
- Spirit Level / Level Threads
- Scaffolding with platform
Material Handling & Storage
On receipt of the Air Handling Units and accessories at site, necessary precautions shall be taken for unloading, shifting & storage, as follows:
All Air Handling Unit received at site shall be inspected to make sure that the materials are as per approved material submittals in terms of their make, model type, country of origin and capacity.
Upon arrival at site, the Air Handling Unit shall be off-loaded carefully at site by the Site Engineer / Site Supervisor using necessary manpower and required equipment to ensure that no damage is caused to the air handling units.
At site all the equipment and materials will be stored in clean / dry place.
Adequate covering by tarpaulin sheets will be done to protect the equipment from deposition of construction dust till it is finally shifted to its installation location.
Any discrepancies and damages found during shipment and storage will be notified and reported to client/consultant for further action suitably.
AHU Preinstallation Requirements
Ensure that clearance is available from civil contractor before commencement of AHU installation works.
Make sure that the work area is clean and safe for carrying out the activities.
Prior to start of ahu installation works, make sure that relevant shop drawings and coordination drawings are approved and issued for construction.
Make sure that no conflicts are observed with other previously installed services, and if there is any issue, it shall be cleared with consultant.
Before installation while issuing the materials from warehouse, double check to make sure that the material issued is as per the approved material submittals.
Air Handling Unit Installation Procedure
The following procedure shall be followed for the installation of Air Handling Units.
Visually inspect the exterior casing of the Air Handling Units for any damages during transporting and transferring of the units.
Cut all banding (if applicable) loose from skid but do not remove the skids until the unit is shifted to the installation area.
Site Engineer shall ensure the availability of manufacturer’s installation manuals / recommendations in order to comply with the same.
Check the equipment weight to ensure that the rigging equipment can handle that safely.
Before installing the unit check the area and make sure proper space shall be available for unit servicing, installing and removing air filters etc.
Proper marking shall be done for the unit location / supports as per approved shop drawing.
Before moving the unit make sure its model number as per approved drawings.
Under direct supervision of the Site Engineer / Site Supervisor, lift the air handling unit, transfer it to the allocated place as per approved shop drawing, position it on to the plinth using the crane if required or rolling as appropriate and feasible.
Ensure that the orientation of AHU’s is matching with direction of supply and return ducts before placing the unit.
Assembling of the air handling unit shall be done by aligning the sections by using the matching bolt of each sections and proper gaskets supplied by manufacturer.
Tighten the bolts and make sure that the complete unit is resting properly on the rubber pads / spring isolators.
Use proper gaskets as supplied by manufacturer while assembling the modules.
Manually rotate the fan wheel to ensure free movement of the shaft and bearings.
Check the base is free from corrosion and galvanized coating is applied, If required.
Inspect the coils and make sure the fins are not damaged.
Check all the filters and make sure these are fixed properly.
Also check the V belt for proper tension.
Installation of AHU Connections
Duct work shall be connected to AHU’s with flexible duct connector as per approved material submittal for supply, return and fresh air duct connections.
Duct thermostat ( sensor ) and test point shall be installed as per approved shop drawing.
Connect the piping network to the air handling unit as per the approved chilled water piping drawing.
Pipe work shall be connected to AHU’s with flexible connection.
Also make sure the installation of all valves and control devices.
Connect the condensate drain pans with drain pipe by using approved materials as per the submittals.
Condensate drain pipes shall be directly connected to the traps and all condensate drain pipe shall be insulated as per approved method statement.
Appropriate traps shall be provided as per approved drawings.
Flushing & cleaning of system shall be done as per chilled water flushing method statement which shall be submitted separately.
Equipment and pipes identification, tagging & labeling shall be carried out after completion of all works as per approved material submittals and mechanical specifications.
All control devices and variable frequency drives connections shall be provided as per approved BMS submittals.
AHU Testing and Commissioning Procedure
Below is a detailed procedure which can be used for AHU Air Handling Units pre commissioning and commissioning activities.
AHU testing and commissioning procedure below gives precise steps and detailed method statement may differ that includes scope of work roles and responsibilities and many other sections.
Pre-Commissioning Procedure For AHU
Ensure that the AHU installation is complete and mechanical completion is approved.
Make sure that no damage has occurred during the period between mechanical completion & precommissioning.
Sealing between the access panels & the frames shall be checked to ensure that there is no leakage of air.
Repair all damages to the equipment finish paint if any.
Verify that proper thermal overload protection is installed in motors, starters and disconnects.
Check all chilled water piping, connected to AHU is with proper valve package, drain, air vents, instruments etc. as per the approved shop drawing.
Lubricate bearings, pulleys, belts and other moving parts with factory recommended lubricants.
Check VAVs/CAVs with controls & wiring done as per requirement of specifications, wiring diagrams and manufacturer instructions.
Also check and verify that all grilles / diffusers are fixed and approved.
Make sure that all VCDs, BDs and fire dampers are open.
Check all motorized dampers are installed, connected with power supply and control wiring is done properly.
Verify that intake dampers are at correct position.
Check filters are clean and fixed properly (Panel & Bag filters)
Verify that electrical power, control panel, VFD and earthing connections are as per manufacturer’s recommendations.
Make sure that field wiring is already tested and approved for continuity and insulation resistance.
Disconnect drive motor, verify proper rotation direction, free fan wheel rotation and smooth bearing operations.
Reconnect fan drive system, align belts and install belt guards.
Check the static & dynamic balancing of the fan impeller.
Set earth leakage and overload relays as per motor nameplate rating.
Check the function of condensate drain system by flowing some water, which should flow freely to its drain point.
BMS & Fire Alarm interface shall be checked in line with their procedures.
Commissioning of Air Handling Units AHU
Ensure that all the precommissioning checks are carried out successfully.
Start AHU by turning on the power supply, and run for 5 minutes.
Measure air flow in the main supply air duct and adjust, if required to set as per design value.
Measure air flow in the return & fresh air and adjust, if required to design values.
Similarly measure air flow in all the branches / outlets.
Set to correct value by adjusting splitter damper, volume control damper etc. in the ducts.
Measure the supply & return air temperature & record it.
Measure the Inlet & outlet water temperature & record it.
The cooling performance shall be calculated & established using the following formula.
Capacity (KW) = Flow (lps) X (Outlet CHW temp (oC)- Inlet CHW temp(oC)/0.239.
The motorized valve shall be checked for proper operation based on the signal from the return air temperature sensor vide DDC controller.
Check the condensate drains freely, the slope of the condensate drain pipes is from 1 to 3% and the drain trap is serviceable.
Record all readings in the final performance check list.
Commissioning of VFDs & controls shall be in line with the approved separate procedure.
Testing & Commissioning of FAHU’s with Heat Recovery Wheel System
Precommissioning Procedure for FAHUs with Heat Wheels
Ensure that the Fresh Air Handling Unit (FAHU) installation is complete and mechanical completion is approved.
Make sure that no damage has occurred during the period between mechanical completion & pre-commissioning.
If required repair all damages to the equipment finish paint.
Verify that proper thermal overload protection is installed in motors, starters and disconnects.
Check all chilled water piping, connected to FAHU is with proper valve package, drain, air vents, instruments, etc as per the approved shop drawing.
Lubricate bearings, pulleys, belts and other moving parts with factory recommended lubricants.
Check all VCDs, BDs and fire dampers are open, all motorized dampers are installed, connected with power supply & controls properly.
Also check filters are clean and fixed properly.
Check for proper electrical power, control panel and earthing connections as per manufacturer’s recommendations, field wiring to be pre-tested for continuity and insulation resistance.
Disconnect drive motor, verify proper rotation direction, free fan wheel rotation and smooth bearing operations. Reconnect fan drive system, align belts and install belt guards.
Set earth leakage and overload relays as per motor nameplate rating.
Check for proper drain of condensate.
Check the air intake louvers are installed properly.
BMS & Fire Alarm interface shall be checked in line with the procedures.
Heat Wheels Precommissioning
Check for proper orientation of the unit.
The labyrinth seal shall be located in the vertical direction across the FAHU.
Check the unit is installed such that the purge sector is facing the conditioned air inside the building, this is the side where the return air enters & supply air leaves the unit.
Check the rotor alignment at the top, bottom, left & right sides, there should be equal spacing on all sides and a minimum 1/4″ spacing from any metal parts for smooth & trouble free operation.
Check all bearing collars and mounting screws are installed as per manufacturer’s recommendations.
Check wheel flatness & seal clearance.
FAHU Commissioning Procedure with Heat Recovery Wheels
Outdoor Intake air – Air entering the FAHU from atmosphere
Supply air – Air leaving the FAHU to the building
Extract air intake – Air entering the Heat Wheel from the building exhaust system
Extract air outgoing – Air leaving the Heat Wheel from the building exhaust system.
Ensure that all the pre-commissioning checks are carried out successfully.
Precommissioning & commissioning of the exhaust fans shall be completed prior to commissioning of the FAHUs, which shall be carried out in line with the approved procedure.
Check for the correct direction of rotation of the fans.
Start FAHU and run for 5 minutes.
Check for proper rotation of the heat wheel.
Measure air flow in the main supply air duct and adjust, if required to achieve the design value.
Measure outdoor intake air flow and adjust, if required to achieve design airflow value.
Set the fan RPM to provide total air quantity within acceptable limits and the required static pressure to operate the system.
Make sure that the fan speed does not exceed the maximum allowable RPM as established by the manufacturer.
It shall be ensured that the final setting of fan speed does not overload the fan motor in any mode of operation.
The total flow shall be measured & recorded by using the duct traverse method and the flow shall be set to 105% of the design value.
Measure the intake & supply air temperature (DB/WB) & record it.
Measure the extract air intake & outgoing temperature (DB/WB) & record it.
Measure & record the supply & intake air relative humidity.
Measure & record the supply & intake absolute relative humidity.
Measure & record the chilled water flow across the FAHU coil.
Calculate temperature efficiency & humidity efficiency.
Measure & record voltage, current & speed of fan motor.
The cooling performance shall be calculated & established using the following formula.
Capacity (KW) = Flow (lps) X (Outlet CHW temp (oC)- Inlet CHW temp(oC)/0.239.
The motorized valve shall be checked for proper operation based on the signal from the return air temperature sensor vide DDC controller.
Check the condensate drains freely & the slope of the condensate drain pipes is from 1 to 3% & the drain trap is serviceable.
Record all readings in the final performance check list.
ATTACHMENTS
- Inspection and Test Plan ITP
- Pre-commissioning check sheet for Heat Recovery System
- Commissioning check sheet for Heat Recovery System
- Performance Test Record for Heat Recovery System
- Risk Assesment