Sprinkler System Installation Procedure

For sprinkler system pipe routing through walls and beams, make sure the appropriate sleeves are provided as per approval shop drawings and specification during the construction of structural elements. Fittings for the changes of direction or elevation shall be selected and installed as per the specification and approved shop drawings. Transfer the pipes from the stores to the areas which are to be installed.

SOFFIT MOUNTED SPRINKLERS

Move scaffold into the position and check that all wheels are locked and outrigger stabilizers are extend to the correct position. Only scaffold that have been duly inspected, certified and tagged shall be used. Mark out vertical support threaded rod, channel position in relation to grid lines, datum marking s per the approved shop drawings. Check the dimensions to the finished face of the wall and / or column; report any discrepancy.

Advertisement:

Secure first section of vertical support to the soffit as per the shop drawing details. Clean thoroughly the pipes, so that all dust is removed. Lift the pipe to the platform using lifts or chine blocks. Fit the bracket support to the pipe. Check the correct elevation of support brackets from the datum. Do not assume that floor / Slab is at correct FFL.

Check the tightness of all the bolts. When sufficient number of support brackets is fixed the pipes may be lifted into the position and secured to the bracket. Adjacent length of pipes shall be joined using the method stated below. For joining the threaded pipes and fittings use jute and shellac.

For grooved fittings, cut the groove depths on pipes as per fitting’s manufacturer data sheet. Apply gasket lubricant around the groove and on the gasket internal. At no time are tools and loose materials to be placed on pipes. The subsequent firefighting pipe work inspection & testing shall be undertaken in accordance with ITP.

WALL MOUNTED SPRINKLERS

Move scaffold tower into the position and check that all wheels are locked and outrigger stabilizers are extend to the correct position. Only scaffold that have been duly inspected, certified and tagged shall be used . Mark out center line of brackets position check the center line is plumb. if using cast-in channel, check that channel is plumb. Mark out elevation of brackets using datum. Do not assume that floor is at correct FFL.

Fix the brackets as shown in approved drawing details. Always check righted of bolts. When sufficient number of support brackets is fixed the pipes may be lifted into the position and secured to the bracket. Adjacent length of pipes shall be joined by using the same method.

Select fittings for changes of direction or elevation and install as per the approved shop drawings. The subsequent pipe work inspection & testing shall be undertaken in accordance with ITP. Make sure Fire alarm devices will be installed in the piping systems as per specification and approved shop drawing as per civil defense requirements.

Install Sprinkler Zone Control Valves, test assemblies and drain risers as per specification and approved shop drawing and manufacturer recommendations and according to civil defense requirements. Ensure Pressure gauges installed as per approved shop drawing and civil defense requirements. Issue request for inspection of installation of Sprinkler systems including supports / brackets, valves, piping specialties and accessories as per approved shop drawing.

Make sure all open pipe works are suitably plugged. Plug all connection ( including Sprinkler Tee-connection / adapters) , branches / drains in preparation to fill the system with water for hydro testing.

HYDRO TESTING PROCEDURE

The entire pipe work will be hydro-statically tested at 10 bars Or 1.5 times the operating pressure. Care should be taken not to exceed maximum capacity of the pipes. Check and ensure that all pipes undergoing test is sufficiently supported and addition of pipe work will not introduce under stress on any support.

Attach the pressure pump / hand pump to the desired location through an isolation valve / by-pass valve and a calibrated pressure gauge to indicate the pressure on the pipe system. When hydraulic test is to be carried out for an installation of multiple floors, pressure gauge shall also be provided at the highest point of the circuit. Ensure test pressure is recorded at highest point of the system. Pressure gauge will be identified with serial numbers matching the submitted copies of calibration certificates.

Attach a drain valve at the lowest part of the pipe system, an air release valve at the highest point along with an isolation valve at the farthest end of the pipe work system to be tested. Once the visible checks are satisfactory, start filling the system with clean water of ambient temperature.

During the water filling process, keep the air release valve, isolation valve open in order to purge any air in the system. Once the pipe is filled with water close the test water inlet and air release valve. Observe any leakage and if found drain the system and immediately rectify the defect before proceeding.

If there is no sign of leakage, increase the water pressure in the pipe work gradually in increment of 2 bars. After increasing by 2 bar pressure hold for 10-15 minutes before applying additional pressure. Check and ensure there is no leakage before proceeding further. Upon reaching the test pressure of 10 bars close and secure the inlet valve. Record the readings in the Hydro Test / Pressure test report sheet and the same to be signed off by consultant. Keep the report in safe custody for future reference.

FLUSHING OF SPRINKLER PIPE SYSTEM

After successful completion of the hydro test/pressure testing, flushing of the system will be    done during the sectional installations of the system and after the completion of the whole Sprinkler system pipe work assembly. Blow down effect if achieved during draining of the system right after completion of Hydro test/ pressure test.

Enough drain points will be left open of the flushing purpose. These points will be located in the lowest point of the area/ zone and the water supply point. The pipe network will be flushed to ensure that the pipes are clean from dust, foreign materials and other construction debris that could have found its way inside the pipes.

The water will be pumped from the water supply point using the existing fire pumps or temporary water supply source, and the lowest points will be connected to the nearest drainage facility via a hose.

Flushing will continue until clear water at the drainage points is achieved. Completely drain the sprinkler piping system, ensure all drain points are fully closed. Make sure to remove all plugs on the sprinkler tee-connection / adapters and install approved sprinkler heads as per specifications and approved layout drawings.

SPRINKLER TYPES

Install pedant, upright, (combined pedant & upright) sidewall, extended coverage- fast response-sidewall, recessed, concealed, in areas as indicated on the approved shop drawings and as per manufacturer recommendation. Any changes proposed must be approved in writing, by the Consultant Engineer.

Make sure all exposed Fire Fighting Sprinkler Pipes, Fittings and accessories will be painted with approved red oxide paint, unless otherwise stated in the specifications. After painting, identification/labeling for Fire Fighting Sprinkler Pipes, Fittings and accessories (with direction of flow) will be done completely as per approved material and specifications.


JOIN FOR LATEST ARTICLES:

Enter your email address & Click Join:

Check Also

Plate Heat Exchanger Installation Method

Plate Heat Exchanger Installation Method

Installation method statement for Plate Heat Exchanger Unless otherwise specified, all heat exchanger installation  shall …