Method Statement For Installation Of MV LV HV Switchgear Panels

1.0 PURPOSE

The purpose of generating this method statement is to define the procedure step by step to implement the correct practices for Medium Voltage switchgear panel installation & its accessories through the guidelines contained herein so as to ensure that the job execution complies with specification and serves the intended function to satisfactory level. This method is also applicable for LV HV Switchgear as well.

2.0 SCOPE

This method statement covers all processes related to Installation of switchgear installationas the following:

  • Installation of switchgear installation and its accessories.
  • This procedure is to be read in conjunction with the relevant ITP, outlining the responsibility and the quality verification to be performed by various parties.

3.0 REFERENCE

Advertisement:

 

  • Approved Shop drawings.
  • Specifications
  • Project HSE plan
  • Project Quality Plan
  • Manfacturer’s Data sheets & Manufacturer recommendations.
  • Regulation of the local Electrical Authority
  • Requirements of Civil Defense Department
  • Approved Material submittal

4.0 DEFINITIONS:

 

PQP                                        : Project Quality Plan

PSP                                         : Project Safety Plan

QCP                                        : Quality Control Procedure

HSE                                        : Health, Safety and Environment

MS                                          : Method Statement

ITP                                         : Inspection Test Plan

QA/QC                                   : Quality Assurance / Quality Control Engineer.

SK                                           : Store Keeper.

WIR                                       : Inspection and Test Request

MIR                                       : Material Verification Record.

MV                                         : Medium Voltage

 

 

 

 

 

5.0 RESPONSIBILITIES:

Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant steps in the procedure:

  • Project Manager
  • Construction manager
  • QA/QC Engineer
  • Site Engineer
  • HSE officer
  • SK

 

            5.1 Project Manager

 

  • Project Manager is the overall responsible for the project in terms of work execution, safety, planning & quality. The Project Manager will maintain the planning progress and coordination of works with the main contractor.
  • The work progress shall be carried out as per planned program and all the equipment’s required to execute the works shall be available and in good condition as per project planned.
  • Specific attention is paid to all safety measures and quality control in coordination with Safety Engineer and QA/QC Engineer and in line with PSP and PQP.

5.2 Construction Manager

 

  • Construction Manager is responsible to supervise and control the work on site.
  • Coordinating with QA/QC Engineer and site Team and foremen for all activities on site.
  • Control and sign all WIR’s before issuing to Consultant approval.

5.3 Site Engineer

 

  • The method of statement to the system shall be implemented according to the Consultant project specifications and approved shop drawings.
  • Provision of all necessary information and distribution of responsibilities to his Construction team.
  • The work progress shall be monitored in accordance with the planned work program and he will provide reports to his superiors.
  • The constant coordination with the Safety Engineer to ensure that the works are carried out in safe working atmosphere.
  • The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for the Inspection for the finished works.
  • He will ensure the implementation of any request that might be raised by the Consultant.
  • Efficient daily progress shall be obtained for all the equipment and manpower.
  • He will engage in the work and check the same against the daily report received from the Foremen.
  • The passage of all the revised information to the Foremen and ensure that it’s being carried out properly.

5.4 QA/QC Engineer (MEP):

 

  • The monitoring of executions of works at site and should be as per the approved shop drawings and project specifications.
  • Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the Consultant.
  • Check and insure that all activities / work done / completed prior to offer for consultant inspection.
  • He will follow and carried out all the relevant tests as per project specifications.
  • Obtain the required clearance prior to Consultant’s inspections.
  • Should acquire any necessary civil works clearances and coordination.
  • Coordinate with site construction team.
  • One who will assist the Consultant Engineer / Inspector during inspection.

5.5 Site Foreman

 

  • The carrying-out of work and the proper distribution of all the available resources in coordination with the Site Engineer on a daily basis.
  • Daily reports of the works are achieved and coordinated with the Site Engineer.
  • Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
  • Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.

5.6 Safety Officer

 

  • The implementation of all safety measures in accordance with the HSE plan and that the whole work force is aware of its proper implementation.
  • The implementation of safety measures is adequate to maintain a safe working environment on the work activity.
  • Inspection of all the site activities and training personnel in accident prevention and its proper reporting to the Construction Manager and the Project Manager.
  • The site is maintained in a clean and tidy manner.
  • Ensure only trained persons shall operate the power tools.
  • Ensure all concerned personals shall use PPE and all other items as required.
  • Ensure adequate lighting is provided in the working area at night time.
  • Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with ladders.
  • Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
  • Ensure safe access to site work at all times.

                        5.7 Store Keeper (SK)

 

  • Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
  • One who will acknowledge the receiving of materials at site in coordination with QA/QC and concerned Engineer.

Installation of MDB SMDB MCC CB medium-voltage-switchgear

  6.0 EQUIPMENTS

 

  • Panel & Accessories shall be in line with approved material submittal and as per approved shop drawing.
  • Tool Box.
  • ortable Hand Tools.
  • Portable Drilling Machine.
  • Grinding Machine.
  • Insulation Testing Equipment.
  • Digital Multi-meter.
  • Measuring Tape.
  • afety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent vest, and safety gloves to ensure maximum ability of safe work and dust mask when require.

 

 7.0 PROCEDURE
7.1 Safety

 

  • Ensure only trained/ Authorised & licensed persons only shall operate the power tools and do the Testing job.
  • Ensure that all personnel’s dealing with live electricity shall be certified and competent.
  • Ensure that Temporary live cable management plan shall develop and implemented.
  • Necessary PPE to be worn while working in energized to be worn while working in energized circuits.
  • Ensure adequate lighting is provided in the working area at night time and if inside the building area to be well illuminated.
  • Safe lifting and shifting of switch gear and its related hazards and risks shall be identifying.
  • Ensure service area/work area openings are provided with barricade, tape, safety nets and warning signage to be provided (Danger: High voltage).
  • Ensure LOTO procedure to be followed and implement comprehensive logout & tag out during execution of work.
  • Emergency response plan & procedure shall be developed and established as per the site condition during the execution of activity.
  • PTW to be applied and obtained to start work on the required area.
  • Calibrated Instruments only to be used.
  • Temporary power supply for T & C shall be taken through standard rated MCBs and RCBs.
  • Power supply used to take temporary power supply shall not have any joints.

Work Sequence And Methodology

  • Check all material delivered to site is inspected properly by QA/QC Engineer and check if it is stored properly as per manufacturer’s recommendations.
  • MIR shall be raised for the inspection of materials received at site by MEP QA/QC Engineer to the Main contractor / Consultant Engineer.
  • Work shall be carried out by the site staff under strict supervision and guidance of the concerned Supervisors / Foremen / Engineers.
  • The MEP QA/QC Engineer shall check all the installations as per the Installation Check list.
  • WIR shall be prepared by MEP QA/QC Engineer and will be submitted to Consultant for their inspection and approval.
  • MEP QA/QC Engineer shall coordinate with other contractors and arrange inspection for installation to the Consultant Engineer.
  • MEP QA/QC Engineer is responsible for all installation activities for getting the work inspected and approved by Consultant Engineer.

7.3 Handling and Storage

On receipt of MV Panel and accessories at site, necessary precautions shall be taken for unloading, shifting and storage, as follows:

 

  • Material shall be stored in a covered / dry space at all the time.
  • All materials received at site shall be inspected and ensured that the materials are as per approved material submittal.
  • Any discrepancies, damage etc., found will be notified and reported for further action.
  • Site Engineer has to ensure that the MV panels used at site are of free from any damage or deformity of any kind. Any minor damages observed shall be repaired suitably and in case if the repairs could not be done properly, the mv panels are to be sent to assembler for rectification, after all formalities carried on.

7.4 General Installation Procedure

 

  • Ensure that the work area is ready and safe to start the installation of Panel.
  • Ensure the installation of MV Panel are carried out in accordance with manufacturer’s installation recommendations, requirement of applicable standards and in accordance with recognized industrial practices and specified in project specification to ensure that installation complies with requirements.

 

  • Prior to start the installation, refer to the approved shop drawings related to the area of installation and ensure that required materials are available at site as per approved material submittals.
  • Ensure the materials are stored properly and there is no mark of damage or deformity of any kind before issuing the material from site store. All materials and accessories should also be free of dust, scale, or oil.
  • Ensure that the issued materials are of approved specifications / submittals and as per the requirement of the area shop drawings. (i.e. Make, Size, Model / Type etc.,).

Installation Procedure for Switchgear Panel

 

 

  1. All required Installation shall be accordance to applicable regulations.
  2. All components such as relays, fuses. CT’s contractor’s meters, breakers size, bus bar sizes etc. shall be verified against the approved material submittal.
  3. All installation shall be carried out according to the approved shop drawing construction for the panels.
  4. Ensure the floor surface is ready with base frames grouted on the open trenches inside the HV room to install the MV Panel.
  5. Minimum clearance of 800 mm shall be maintained at rear side of the panel so that easy access for termination of cables and other maintenance works can be carried out.
  6. MV Panel shall be installed in accordance with the Manufacturer’s recommendations, approved site layout and as per site requirement.
  7. All knockouts made on the panel covers shall be filed and provided with grommets to avoid sharp edges and unused knockouts shall be covered.
  8. The connection of bus bar trunking with MV panel shall be done rigidly with proper supports.
  9. Cables bending radius should be not less than 12 times of the cable diameter in line with the Manufacturer’s recommendation & as per Specifications
  10. Cable pulling, termination & crimping shall be done as per cables method statement.
  11. Termination of cables shall be done using approved material submittal for cable glands and lugs. Glanding and connections should be done only by competent technicians / electricians.
  12. Switch gear shall be provided with proper earthing connections as per approved shop drawings and AUTHORITY regulations.
  13. Manufacturer recommendations are to be followed for all relay and other breaker current settings, as per the total connected loads and the discrimination study of the system.
  14. Identification labels of approved type shall be fixed on the MV panel.
  15. Ensure that all cable entries and other openings of Electrical / HV Room, Wall / Floor are carried out with proper approved sealant.
  16. The manufacturer’s representative to verify the site installations and provide acceptance of same prior to Energization of MV Panel after obtaining clearance from Site Engineer.
  17. Ensure that Adequate A/C provided to the MV panel room and the Unit of the A/C shall not be installed inside MV room as per contract drawing. The A/C unit shall be installed outside the room and to be connected with duct to MV room. And no water services allowed inside HV room as per AUTHORITY regulation.
  18. Connecting cables between the switchboard and battery unit, and between the switchboard and AC control panel shall be neatly run on cable trays supplied by the Contractors.
  19. The connecting cables between the switchboard and battery unit shall be at least 4 mm in size and shall be run in a ring configuration. Physically, the cables for entry and exit of the same loop should not be the same. All wiring and termination of connecting cables shall be carried out by the Contractor. Conductors used for AC and DC circuits shall not be mixed in the same multi-conductor cable.
  20. Upon completing the installation of MV Panel, ensure all the works carried out as per AUTHORITY regulations.
  21. Raise (WIR) for installation of switchgear Panel along with glanding and termination to Consultant.
 8.0  ATTACHMENTS
  • Inspection and Testing Plan                                
  • Checklist
  • Risk Assessment
Advertisement:

JOIN FOR LATEST ARTICLES:

Enter your email address & Click Join: