How To Do Installation of Suspended False Ceilings Materials

A dropped ceiling or false ceiling is a secondary ceiling, hung below the main (structural) ceiling. It may also be referred to as a drop ceiling, T-bar ceiling, false ceiling, suspended ceiling, grid ceiling, drop in ceiling, or drop out ceiling and is a staple of modern construction and architecture in both residential and commercial applications.

How To Install False Ceiling Materials

A typical dropped false ceiling consists of a grid-work of metal channels in the shape of an upside-down “T”, suspended on wires from the overhead structure. These channels snap together in a regularly spaced pattern of cells. Each cell is then filled with lightweight ceiling tiles or “panels” which simply drop into the grid. The primary grid types are “Standard 1″ (15/16 face), Slimline (9/16” grid), and concealed grid.

In the United States the cell size in the false ceiling suspension grids is typically either 2 ft × 2 ft or 2 ft × 4 ft and the ceiling tiles are the same size. In Europe the cell size in the suspension grids is 600×600 mm, while the ceiling tiles are slightly smaller at 595mm x 595mm or 595mm x 1195mm.

Equipment Required For Installation of Suspended false Ceilings Materials

  • Leveling Instruments
  • Line dory
  • Cutting Tool
  • Measuring tape
  • Spirit level
  • Screw driver
  • Drilling Machine
  • Hammer
  • Wire Cutter
  • Nail Gun with cartridge
  • Mobile scaffolds
  • ladders

Preparatory Works for false ceiling

  • Ensure that materials, samples, shop drawing and method statement for the installation of false ceiling is submitted and approved by the Engineer.
  • Aluminum tiles plain and perforated and gypsum plaster tiles of specified type and thickness shall be used.
  • Mock up of suspended false ceiling systems shall be arranged at location designated by the client for the final approval.
  • Approved Mock Up and sample shall be available at site and the materials delivered to site shall be checked with respect to the approved sample.
  • Ensure materials delivered in original packaging, bearing name of manufacturer and product.
  • Ensure that materials are stored in an enclosed area and protected from damages.
  • Ensure that Plaster works and painting work shall be done up to the required height.
  • Verify Layout of false ceiling tiles showing the position of cut tiles, pattern, etc are approved by the Engineer.
  • Ensure that setting out of fixing of MEP services and ceiling suspension system shall be similarly coordinated.
  • Ensure that MEP services have been installed and clearance obtained from the concerned department.
  • Proper working platform shall be provided for the safe access of works.

False Ceiling Procedure

FALSE CEILING INSTALLATION STEPS

  • False Ceiling height in each area shall be marked in relation to the elevation of bench marks & transferred by water level
  • Powder coated angles as per approved materials and section details of false ceilings will be fixed on level markings with screws and plugs
  • The grids shall be laid out as per reflected ceiling layout.
  • All setting out shall be carried out according to the working / shop drawing.
  • The hangers will be installed according to spacing and level required.
  • Main –T-sections as per approved materials will then be tied to hangers at sufficient intervals
  • Cross T-BAR will then be fixed in between all the Main-T-sections to its lock position perpendicular to it at sufficient intervals
  • Leveling shall be carried out to prevent any subsequent download movement.
  • During these installation process MEP items installed were to be taken care, ensuring no damages.
  • Where hangers cannot be fixed at the recommended spacing due to the presence of services, equipment or other obstructions, a sub-grid of appropriate span & performance shall be used with prior permission from the Customer.
  • It shall be securely supported to prevent lateral movement.
  • Access panels and MEP opening location to be determined and set according to approved shop drawings details.
  • MEP clearance shall be obtained prior to commencing ceiling tile /gypsum board works.
  • Upon completion of framing work including final adjustment to ensure entire suspension is level, the ceiling boards were then be fixed up at proper intervals.
  • Air terminal devices like grills or similar equipment shall be incorporated in the ceiling as specified.
  • After ensuring the ceiling boards/tiles were installed accordingly and acceptable flatness, sealing up of joints will proceed.
  • Final inspection for the false ceiling works will be made by the Engineer and contractor and to be rectified to any comments given by them.

Discover more from Method Statement HQ

Subscribe to get the latest posts to your email.

error: Content is protected !!

Discover more from Method Statement HQ

Subscribe now to keep reading and get access to the full archive.

Continue reading